FINANCIAL: Budget Changes

 

 

OVERVIEW  

**NOTE THESE PAGES ARE CURRENTLY IN DRAFT FORM.  PLEASE CHECK BACK FOR UPDATES

What is a Budget Change

  • In short definition, a Budget Change is the process of moving money from one phase code to another.
  • Previously this was handled through the Internal Change Order process.

 

Brinkmann Standards

  • Budget Change:
    • Once the budget is imported from Vista, any changes to budget have to come from Procore.
    • Changes to the original budget will be changed by accounting.
  • Approved Cost Types are:
    • Subcontracts
    • Purchase Orders
    • Labor
    • Equipment
    • Material
    • Tax
    • Other

Notable Changes to past procedures

  • The 18000 phase codes are no longer used.
  • Phase Code dashes will now only be used to represent multiple buildings.
  • You can now utilize multiple cost codes on a commitment (subcontract).  See the commitments walkthrough for further information.
  • Numbering in Procore for cost codes will look different due to a difference between how Vista lists code vs. how Procore uses it.
  • To add an additional cost code to your project after initial set up you must reach out to the accounting department to have them added to your project.
TO CREATE A BUDGET CHANGE  
  1. Navigate to your Budget Tool.
  2. Click on the Orange "Create a Budget Change" button located in the top right Corner.
  3. This will create a Budget Change for your project.
    1. Number is auto generated, but can be manually adjusted.
  4. Name your Budget Change, and provide a description.
  5. Input your adjustments.
    1. The first line in your adjustment is the full amount of the change. Each consecutive line supplements that information.

Example:  Original Budget Amount: Drywall for $100,000

How to set up the Budget

Cost Code 9250

  • Cost Type Other: $50,000
  • Cost Type Subcontracts: $50,000

You buyout the drywall subcontractor for $70,000 and you also want to allocate $10,000 for Brinkmann Labor for general clean-up

Budget Change

  • Move $20,000 from Cost Type Other to Cost Type Subcontracts
  • Move $10,000 from Cost Type Other to Cost Type Labor
  • Update Budgets
    • 9250 - Other: $20,000
    • 9250 - Subcontracts: $70,000
    • 9250 - Other: $10,000

The main budget change screen will indicate if the change has synced with Vista (ERP)

When a Budget Change is created, it will automatically create a Change Event.

When the Budget Change is complete, ensure you update the Change Event status to "CLOSED".

ROM INFORMATION ESTIMATED COST AT COMPLETION (ECAC)
  • The ROM column on the budget screen, after projected budget is complete, will include amounts only when a PCO hasn't been created. 
    • Open status will put it in the column.
    • PCO creation will cause the amount to drop off
  • The ROM is not reflected in projections.  Projection columns include only cost and revenue. 
 
   

PROCORE STANDARDS & BEST PRACTICES

The Budget tool allows you to build and manage a comprehensive budget throughout a project's lifecycle. By eliminating the need for double-entry of contract modifications and change order values into complex spreadsheets, you'll have greater insight into how seen and unforeseen changes impact the bottom line. Take control over complicated project factors when evaluating and forecasting your project's completion costs.

  • Import an existing budget or build a comprehensive project budget that can be exported to the Microsoft Excel or PDF formats
  • Review financial performance for a single project or across multiple projects
  • Share the status of your budget with your team so they can make informed decisions in the field
  • Generate detailed budget reports showing budget modification, buyout summaries, line item details, and more

There are no items that match your search query.

Configuration Tasks
ERP Integrations
 Tip

To browse and search all Procore training videos, visit our video library.

Set Up a Budget
 
Set Up a Budget - Owner
 
Set Up a Budget - Specialty Contractor
 
Add New Line Items to a Budget - General Contractor
 
Add New Line Items to a Budget - Owner
 
Add New Line Items to a Budget - Specialty Contractor
 
Create a Budget Change
 
Create a Budget Modification
 
Create a Budget Modification - Owner
 
 
 
 
Set Up Budget Views - Specialty Contractor
 
Buyout Savings Budget View
 
Buyout Savings While in a Buyout Budget View
 
Current/Revised Buyout Budget View
 
Budget Forecasts, Projections, and Reports
 
Budget Forecasts, Projections, and Reports - Specialty Contractor
 
Change Order Analysis
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Specialty contractor as a Client - Set Up Budget Views

 

Owner - Set Up a Budget

 

Owner - Navigate the Forecasting Tab

 

General Contractor - Navigate the Forecasting Tab

 

Specialty Contractor - Navigate the Forecasting Tab

 

Owner - Create a Budget Modification

 

Budget Modifications

 

Owner - Add New Line Items to the Budget

 

Specialty contractor as a Client - Create a Direct Cost

 

Specialty contractor as a Client - Add New Line Items to a Budget

 

Add New Line Items to a Budget

 

Specialty contractor as a Client - Budget Forecasts, Projections, and Reports

 

Specialty contractor as a Client - Setup a Budget

 

Set Up Configurable Budget Views

 

Specialty contractor as a Client - Create a Budget Modification

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Budget Forecasts, Projections, and Reports

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
Create a Budget Modification
 
 
Budget Forecasts, Projections, and Reports
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Budget Modifications

 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
Create a Budget Modification
 
 
Budget Forecasts, Projections, and Reports
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Budget Modifications

 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Budget Modifications

 
Set Up a Budget
 
Add New Line Items to a Budget - General Contractor
 
Create a Budget Change
 
 
Budget Forecasts, Projections, and Reports
 
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Add New Line Items to a Budget

 
 
Set Up a Budget
 
Set Up a Budget - Owner
 
Set Up a Budget - Specialty Contractor
 
Add New Line Items to a Budget - General Contractor
 
Add New Line Items to a Budget - Owner
 
Add New Line Items to a Budget - Specialty Contractor
 
Create a Budget Change
 
Create a Budget Modification
 
Create a Budget Modification - Owner
 
 
 
 
Set Up Budget Views - Specialty Contractor
 
Buyout Savings Budget View
 
Buyout Savings While in a Buyout Budget View
 
Current/Revised Buyout Budget View
 
Budget Forecasts, Projections, and Reports
 
Budget Forecasts, Projections, and Reports - Specialty Contractor
 
Change Order Analysis
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Specialty contractor as a Client - Set Up Budget Views

 

Owner - Set Up a Budget

 

Owner - Navigate the Forecasting Tab

 

General Contractor - Navigate the Forecasting Tab

 

Specialty Contractor - Navigate the Forecasting Tab

 

Owner - Create a Budget Modification

 

Budget Modifications

 

Owner - Add New Line Items to the Budget

 

Specialty contractor as a Client - Create a Direct Cost

 

Specialty contractor as a Client - Add New Line Items to a Budget

 

Add New Line Items to a Budget

 

Specialty contractor as a Client - Budget Forecasts, Projections, and Reports

 

Specialty contractor as a Client - Setup a Budget

 

Set Up Configurable Budget Views

 

Specialty contractor as a Client - Create a Budget Modification

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Budget Forecasts, Projections, and Reports

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Budget

diagram_budget_budget-setup.png

Add a Budget View for Real-Time Labor Costing

diagram_budget_real-time-labor-costing-budget-view.png

Set Up the 'Procore Labor Productivity Cost' Budget View

diagram_budget_procore-labor-productivity-cost-budget-view.png

Budget

The following table highlights which user permissions are required to perform the described user action.

icon-mindtouch-table-check.png+ : Indicates that one or more granular permissions are available for the task. See the relevant tutorial or Grant Granular Permissions in a Project Permissions Template for more information.

erp-integration.png : Indicates your company's Procore account must be configured to work with an integrated ERP system

Task None Read Only Standard Admin
Add a Budget Line Item   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Add a Budget View for Real-Time Labor Costing This task must be completed in the Company's Admin tool. Also requires Procore's Field Productivity tools. 
Add Budgeted Production Quantities to a Project's Budget       icon-mindtouch-table-check.png
Add the Columns for the 'Budget Changes' Feature to a Budget View This task must be completed in the Company's Admin tool.
Add a Goods & Services Tax (GST) to a Budget 1       icon-mindtouch-table-check.png
Add a Partial Budget Line Item     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Apply Advanced Forecasting Curves       icon-mindtouch-table-check.png
Apply the View, Snapshot, Group, and Filter Options on a Budget View   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Approve Budget Changes   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Configure Settings: Budget       icon-mindtouch-table-check.png

Legacy  Create a Budget Modification

    icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create Budget Changes   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Create a Budget Snapshot     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create a Custom Budget Report 2       icon-mindtouch-table-check.png
Create a Custom Financial Line Items Report to Compare Budget Snapshots This task must be completed in the Reports tool.
Delete a Budget Line Item     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Delete Budget Changes   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Edit a Budget     icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Edit Budget Changes   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Export a Budget to an Integrated ERP System icon_CL_ERP_Integrations_w50.png       icon-mindtouch-table-check.png
Export Budget Changes   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Import a Budget   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Import a ProEst Estimate for the Budget SOV  3     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Import Installed Production Quantities for the Labor Productivity Cost Budget View       icon-mindtouch-table-check.png
Lock a Budget   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Read a Budget   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Retrieve a Budget from ERP Integrations Before Acceptance tool-icon_erp-integrations_web-company-level.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Set up a Budget in a New Procore Project     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Send a Budget to ERP Integrations for Accounting Acceptance icon_CL_ERP_Integrations_w50.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Set Up a Budget View for Custom Reporting This task must be completed in the Company Admin tool.
Set Up a New Budget View This task must be completed in the Company Admin tool.
Set Up a New Forecasting View This task must be completed in the Company Admin tool. 
Unlock a Budget       icon-mindtouch-table-check.png
Unlock a Budget with Budget Modifications       icon-mindtouch-table-check.png
Use the 'Forecast to Complete' Feature     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
View Budget Changes   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
View Budget Change Detail for a Budget Line Item   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
View Budget Reports  4   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
View and Filter the Change History of the Budget       icon-mindtouch-table-check.png
Void Budget Changes     icon-mindtouch-table-check.png icon-mindtouch-table-check.png

1 This task also requires 'Admin' permissions on the project's Client Contracts, Funding, or Prime Contracts tool. 

2 Also requires 'Admin' permissions on the Company level Reports tool.

3 These steps require that your company has enabled the ProEst by Procore integration.  

4 The Reports tool must be an active Project Tool. See Add and Remove Project Tools

Below are the notable changes to the project's Budget tool.

Recent Changes

No recent notable changes.