How do I export cost forecast data from a Procore budget to Viewpoint® Vista™

Answer

For companies that have integrated Procore with Viewpoint® Vista™, you can import your real-time actual cost data from Viewpoint® Vista™ into Procore's Budget tool. This lets project team's leverage their Viewpoint® Vista™ cost data with the 'Estimated Cost' value in a Procore budget to calculate the budget's 'Estimated Cost at Completion' and 'Forecast to Complete' values. This ability provides your project's accounting team with the complimentary benefit of being able to access Procore's 'Estimated Cost at Completion' values in Viewpoint® Vista™.

To turn on forecasting/projections: 

  1. Navigate to the project Budget tool
  2. Click on the settings icon-settings-gear-android.png icon.
  3. Change the following settings:
    • Default ERP Budget View: ERP Job Cost Detail Budget
    • Designated Estimated Cost at Completion Column: Estimated Cost at Completion

Which data fields are exported?

A Forecasting export will create a JC Cost Projection in Viewpoint® Vista™.


PROCORE
Exports data from Procore to Viewpoint® Vista™  Imports data from Viewpoint® Vista™ to Procore
Viewpoint® Vista™
Vista Job ID erp-orange-arrows.png   Job ID
Cost Code erp-orange-arrows.png   Phase
Cost Type erp-orange-arrows.png   Cost Type
Estimated Cost at Completion erp-orange-arrows.png   Projected Cost (ProjFinalCost)

 

*You can also manually add a Batch Date within the Procore export screen which will export to the Batch Month in Vista for this transaction. 

 

What are the requirements?

  • The Budget tool must be added to Procore's Project Tools menu. 
  • The company's Procore account must be integrated with Viewpoint® Vista™. 
  • The Viewpoint® Vista™ cost data from the original estimate must first be synced with Procore's Budget tool. 
  • The imported data and the 'Estimated Cost to Completion' value in Procore can then use Procore's 'Forecast to Complete' options to calculate the values to export to the integrated Viewpoint® Vista™ system. 
  • When exporting forecast information for a project, ALL of the budget views that include ERP source columns on your integrated projects must be set to use the same calculations shown above for the  'Forecast to Complete' and 'Estimated Cost at Completion' columns. If not, it is possible that the export will send incorrect or unexpected values to Viewpoint® Vista™. To learn more about setting up budget views, see Set up a New Budget View.
 Phased Release: Budget Changes

Some ERP integrated clients may have already transitioned from Budget Modifications (Legacy) to the new Budget Changes experience. The legacy experience will continue to be available until October 16, 2023. To learn more about the timeline for migration, see: Common Questions.

Choosing to use the new Budget Changes experience will not impact the function of your ERP integration, or the steps in this tutorial. If you encounter a step with directions regarding Budget Modifications, and you have already adopted Budget Changes, please take the same action in Budget Changes as you would in Budget Modifications.

To learn more about the new Budget Changes experience, see About Budget Changes.