How do I export cost forecast data from a Procore budget to Viewpoint® Vista™
Answer
For companies that have integrated Procore with Viewpoint® Vista™, you can import your real-time actual cost data from Viewpoint® Vista™ into Procore's Budget tool. This lets project team's leverage their Viewpoint® Vista™ cost data with the 'Estimated Cost' value in a Procore budget to calculate the budget's 'Estimated Cost at Completion' and 'Forecast to Complete' values. This ability provides your project's accounting team with the complimentary benefit of being able to access Procore's 'Estimated Cost at Completion' values in Viewpoint® Vista™.
To turn on forecasting/projections:
- Navigate to the project Budget tool
- Click on the settings
icon.
- Change the following settings:
- Default ERP Budget View: ERP Job Cost Detail Budget
- Designated Estimated Cost at Completion Column: Estimated Cost at Completion
Which data fields are exported?
What are the requirements?
- The Budget tool must be added to Procore's Project Tools menu.
- The company's Procore account must be integrated with Viewpoint® Vista™.
- The Viewpoint® Vista™ cost data from the original estimate must first be synced with Procore's Budget tool.
- The imported data and the 'Estimated Cost to Completion' value in Procore can then use Procore's 'Forecast to Complete' options to calculate the values to export to the integrated Viewpoint® Vista™ system.
- When exporting forecast information for a project, ALL of the budget views that include ERP source columns on your integrated projects must be set to use the same calculations shown above for the 'Forecast to Complete' and 'Estimated Cost at Completion' columns. If not, it is possible that the export will send incorrect or unexpected values to Viewpoint® Vista™. To learn more about setting up budget views, see Set up a New Budget View.