Objective

To view the change history of the budget, which details every change made to the budget in Procore.

Things to Consider

  • Required User Permission: 'Admin' level permissions on the Budget tool. 

Steps

  1. Navigate to the project's Budget tool.
  2. Click the Change History sub tab.
  3. The change history outlines the change, who performed the change, details of the change, from what it was changed from and what it was changed to, and the date and time of the change. Items in this history cannot be deleted.

 