Create a Subcontractor Invoice on Behalf of an Invoice Contact
Objective
To create a downstream invoice as an invoice administrator on behalf of an invoice contact.
Background
An invoice administrator can also gather digital or paper invoices from a project's external collaborators, outside of Procore. Once you have the invoices in hand, you can create subcontractor invoices in Procore on their behalf. When using this option, you don't need to provide external collaborators with invoice contact permissions for your project's commitments.
Things to Consider
- Required User Permissions:
- You must be an invoice administrator.
- Additional Information:
- An invoice administrator can:
- Create invoices for all of a project's commitments.
- Edit amounts on a Schedule of Values when the invoice is in the Draft or Revise & Resubmit status. When multiple invoices exist for one commitment during one billing period, you can only amounts on the latest invoice.
- For users legally required to provide claimants with a payment schedule, see Create a Payment Schedule.
- An invoice administrator can:
Prerequisites
- Create a Commitment
- Place the commitment is the Approved or Completed status. See What are the default commitment statuses in Procore?
Steps
- Open the New Invoice Page
- Update the General Information Card
- Update the Schedule of Values Card
- Set and Release Retainage on SOV Line Items
- Add Attachments
- Save the Invoice
- Optional: Send an Invoice with DocuSign©
Open the New Invoice Page
New invoices are always created in the project's Commitments tool. The first step is to open the 'New Invoice' page as follows:
- Navigate to the project's Commitments tool.
- In the Contracts table, locate the commitment that you want to create the invoice for.
- Click the Number link to open the commitment.
Tip
Want to collect signatures using the Procore + DocuSign© integration? To do this, click Edit Contract button. Next, place a mark in the Sign with DocuSign© checkbox on the 'General Information' card in the commitment contract. If you add a mark, click Save now. Otherwise, click Cancel. Important things to note:
- The DocuSign© integration must be enabled. See Enable or Disable the DocuSign® Integration on a Procore Project.
- Your DocuSign© account must be linked to Procore. See Link Your DocuSign® Account to a Procore Project.
- In the contract, click the Create button. Then choose the Create Invoice option from the drop-down menu.
Notes
- To use the Create Invoice menu option, the commitment contract must be in the Approved or Complete status. See What are the default commitment statuses in Procore?
- To expedite the invoice creation process, it is also helpful to ensure the following is complete before proceeding with creating an invoice:
- A Contract Company is assigned to the commitment contract. See Create a Commitment.
- An invoice contact from the contract company is assigned to the commitment contract. See Add Invoice Contacts to a Purchase Order or Subcontract.
- The line items in the Subcontract Schedule of Values on the commitment contract are approved. See What is a Subcontractor Schedule of Values?
- The billing period for the new invoice has been created in the project's Invoicing tool. See Create Automatic Billing Periods or Create Manual Billing Periods.
- Continue with the next step.
Update the General Information Card
The next step is to update the 'General Information' card as follows:
- In the new invoice, add and/or verify the data in the General Information card:
Tip
Need to edit an existing invoice? If you are editing an existing invoice, you can click the Edit button that appears in the top-right corner of the General Information card. This button only appears on the card after the new invoice is saved.- Contract Company
Shows the name of the company that completed the contracted work associated with this invoice. This company is assigned to the commitment contract during creation. See Create a Commitment. - Status
Select a status for the invoice from the drop-down list. On a new invoice, Procore's default status is Draft.Notes
- To learn about statuses, see What are the default statuses for Procore invoices?
- If an invoice is ready to be reviewed by an invoice administrator, remember to change its status to Under Review.
- After the invoice administrator reviews an invoice, its status can be change to Approved or Revise and Resubmit as needed.
- Users with 'Standard' permission on the Commitments tool can only edit invoices in the Draft or Revise and Resubmit status.
- Optional: Invoice #
Enter the downstream collaborator's invoice number in the Invoice # box. - Billing Period
Select the date range for the billing period. Procore automatically selects the current billing period by default.Notes
- Invoice administrators are responsible for creating billing periods. For instructions, see Create Automatic Billing Periods or Create Manual Billing Periods.
- Users with 'Admin' level permissions on the Commitments tool can select any billing period from the drop-down list.
- Users with 'Standard' level permissions on the Commitments tool can only select a billing period that does NOT have an invoice associated with it.
- Billing Date
Procore automatically selects the default date defined in the current billing period. This is a required field. - Period Start
Procore automatically selects the default start date defined in the current billing period. This is a required field. - Period End
Procore automatically selects the default start date defined in the current billing period. This is a required field.Note
The 'Billing Period' date in Procore is intended to align with the work being performed on a project so project managers can track and report the affect of invoices on the project's budget. However, if your accounting team defines billing periods differently, it is recommended that you keep the 'Billing Period' entry and then manually enter your unique accounting dates in the 'Billing Date,' 'Period Start,' and 'Period End' fields. - Optional: Payment Date
Enter the date the payment should be made to the 'Contract Company'. - Optional: Submitted Date
Enter the date the payment should be submitted to the 'Contract Company'.
- Contract Company
- Continue with the next step.
Tip
Want to save your invoice now? If you want to click the Save button on the invoice, you may do so now. Procore will create the new invoice and you must click the Edit buttons on each card in the invoice to proceed with the data entry. The instructions in this tutorial assume that you will proceed with the creation process before clicking Save.
Update the Schedule of Values Card
The next step is to update the 'Schedule of Values' card. The available data entry fields depend upon the contract's accounting method setting: the Unit/Quantity Based method or the Amount Based method.
Tip
How do I set the accounting method on a contract? To learn how, see How do I set the accounting method for a contract or funding?For Commitments Using the Unit/Quantity Based Accounting Method
Follow these steps when the line item data is using the 'Unit/Quantity Based' accounting method.
Important
- These instructions describe how to update the SOV line items and assume you are using Procore's default column layout. Because you can personalize your column layout, it is important to note the column layout in your environment may be different.
- To reset a personalize column layout to Procore's default setting at any time, click the vertical ellipsis in any column header and choose Reset Columns from the Overflow menu.
- If you are an invoice administrator and want to edit the 'Schedule of Values' card later, the invoice must be in the 'Draft' or 'Revise and Resubmit' status. See What are the default statuses for Procore invoices?
- Scroll down to the 'Schedule of Values' section of the new invoice.
- Click a line item in the 'Schedule of Values' section to select it.
- Review and complete the fields in the following columns for each line item(s) that will be paid for by the invoice:
- Total Progress %: Enter a percentage amount to represent the total work progress to date. For example, if this is your first invoice and 50% of the work has been installed, enter 50% in this field. This automatically updates the quantity and dollar values in these columns: 'New Quantity', 'Total Completed & Stored To Date', and 'Balance to Finish.'
- New Quantity: If you would prefer, you can also enter a dollar amount to represent the dollar value of the work progress to date. For example, if you didn't enter 50% in the 'Total Progress %' column, you may want to enter $500.00 in this field to indicate that half the total 'Quantity' from the contract has been installed This automatically updates the percentage amount in the 'Total Progress %' field.
Example
The illustration below shows you how Procore automatically updates column values on a line item when you enter a percentage amount in the 'Total Progress %' column. If you prefer to enter a quantity amount in the 'New Quantity' column, your entry automatically updates the percentage value in the 'Total Progress %' column. Whichever method you choose for your data entry, Procore also automatically calculates the values in the 'Total Completed & Stored to Date' and 'Balance to Finish' columns.
For Commitments Using the Amount Based Accounting Method
Follow these steps when the line item data is using the 'Amount Based' accounting method.
Important
- These instructions describe how to update the SOV line items and assume you are using Procore's default column layout. Because you can personalize your column layout, it is important to note the column layout in your environment may be different.
- To reset a personalize column layout to Procore's default setting at any time, click the vertical ellipsis in any column header and choose Reset Columns from the Overflow menu.
- If you are an invoice administrator and want to edit the 'Schedule of Values' card later, the invoice must be in the 'Draft' or 'Revise and Resubmit' status. See What are the default statuses for Procore invoices?
- Scroll down to the 'Schedule of Values' section of the new invoice.
- Click a line item in the 'Schedule of Values' section to select it.
- Review the data for each line item(s) on the invoice's Schedule of Values:
- Item Number. Shows the line item number on the invoice's Schedule of Values.
- Budget Code. Shows the budget code assigned to the invoice's line item on the Schedule of Values.
- Description of Work. Shows the description entered on the commitment contract the invoice line item.
- Scheduled Value. Shows the scheduled value of the line item on the commitment contract. This is the contracted value of the line item.
- Work Completed from Previous Application (%). If previous invoices have been created for the commitment contract, this cell shows a percentage value that represents the work completed during previous billing periods for the commitment contract.
- If you will be submitting an invoice for work completed during the current billing period, you have these options:
- Optional: Total Completed & Stored to Date (%). Enter the percentage of work completed and materials stored to date. For example, if this is the first invoice for a commitment contract and you completed half of the work for the line item during this billing period, you can enter 50% here. If this is not the first invoice for the commitment, you might prefer to add your data entry in the 'Work Completed this Period' column (detailed below) instead.
Note
If you have previously created invoices for this commitment contract, its important to remember that the value entered here represents the total work completed and the total materials stored to date. An entry in 'Total Completed & Stored to Date (%)' column represents all work and stored materials for both the current billing period for this invoice and any invoice(s) for past billing periods.- The currency amount in the 'Work Completed this Period' column. If the line item has a scheduled value of $500.00, Procore enters $250.00, which is 50% of the work.
- The currency 'Total Completed & Stored to Date ($)' column. Procore adds $250.00 to this column. This column also shows the cumulative value from previous invoices.
- The amount in the 'Balance to Finish' column. This subtracts your current entry from the 'Scheduled Value' column, to show the work remaining on the commitment contract.
- The amount in 'Work Retainage this Period ($)' column. This calculation is based on the amount entered and the entry in the 'Work Retainage this Period (%) column on the line item.
OR
- Optional: Work Completed this Period. Enter an amount to represent the work completed for the current billing period. For example, if you completed half of the work for the line item, you could enter the currency amount here (instead of a percentage value in 'Total Completed & Stored to Date (%)' column. For example, you could enter $250.00 in the column (instead of 50% in the 'Total Completed & Stored to Date (%)' column). If you enter a value here, Procore automatically calculates the line item data as follows:
- The percentage amount in the 'Total Completed & Stored to Date (%)' column. If the line item has a scheduled value of $500.00, Procore add $250.00, which is 50% of the work to the value. Remember that the value in this column represents the total work on the current invoice and any invoice(s) from past billing periods.
- The currency 'Total Completed & Stored to Date ($)' column. Procore adds $250.00 to this column. This column also shows the cumulative value from previous invoices.
- The amount in the 'Balance to Finish' column. This subtracts your current entry from the 'Scheduled Value' column, to show the work remaining on the commitment contract.
- The amount in 'Work Retainage this Period ($)' column. This calculation is based on the amount entered and the entry in the 'Work Retainage this Period (%) column on the line item.
- Optional: Total Completed & Stored to Date (%). Enter the percentage of work completed and materials stored to date. For example, if this is the first invoice for a commitment contract and you completed half of the work for the line item during this billing period, you can enter 50% here. If this is not the first invoice for the commitment, you might prefer to add your data entry in the 'Work Completed this Period' column (detailed below) instead.
- If you will be submitting an invoice to bill for new materials received and being stored during this billing period, enter the following:
Note
New to billing for stored materials in Procore? To learn more about billing for materials stored in a downstream invoice, see How do I bill for stored materials in a subcontractor invoice?
- New Materials Stored. Enter a currency amount of any new materials being stored on the job site (or in a storage facility) for the current billing period. The amount you enter her should exclude the costs entered in the 'Work Completed this Period' column.
- Previous Materials Stored. Enter a currency amount for the materials that were recorded as being stored on the previous invoice.
- Materials Presently Stored. Shows the currency amount of the materials being stored during the current billing period.
- Total Completed & Stored to Date ($). Shows the currency amount of the work completed and materials stored on the job site for the current invoice and on invoice(s) for past billing period(s).
- Balance to Finish: Shows the remaining currency amount for the line item. This represents the work that has not yet been completed.
- Optional: If you want to set or release retainage on the SOV line items, continue with the next step.
Set and Release Retainage on SOV Line Items
If you want to set and release retainage on the line items in the SOV, follow these steps:
- Choose from these options to select the line items:
- To select all of the line items in the SOV, click the checkbox in the 'Item Number' header of the data table.
OR - To select individual line items, mark the checkbox(es) in the 'Item Number' column for the desired line item(s).
- To select all of the line items in the SOV, click the checkbox in the 'Item Number' header of the data table.
- In the Schedule of Values, click the Edit button.
- Optional: If you are an invoice administrator who wants to set the retainage for the invoice, do the following:
- Mark one or more Item Number check boxes. Then click the pencil icon above the data table in the Schedule of Values.
This opens the Edit pane on the right side of the page. - Enter the retainage values to apply to the selected line item(s):
- Work Retainage This Period (%). Enter a percentage amount to indicate the percentage of work retainage to be released this billing period.
- Retainage Released. Enter a percentage amount to indicate the percentage of retainage released.
- Materials Retainage (%). Enter a percentage amount to indicate the percentage of work retainage to be released this billing period.
- Click Apply.
- Mark one or more Item Number check boxes. Then click the pencil icon above the data table in the Schedule of Values.
- Choose from these options for entering work retainage:
- Work Retainage This Period ($). Shows the currency amount for the work retainage this period. The value that appears here is based on your entry in the 'Work Completed this Period' column. An entry in this cell lets Procore automatically calculate the percentage value in the 'Work Retainage This Period (%)' column.
OR - Work Retainage This Period (%). Enter a percentage amount for the work retainage that you are requesting to be released this period. An entry in this cell lets Procore automatically calculate the currency value in the 'Work Retainage This Period ($)' column.
- Work Retainage This Period ($). Shows the currency amount for the work retainage this period. The value that appears here is based on your entry in the 'Work Completed this Period' column. An entry in this cell lets Procore automatically calculate the percentage value in the 'Work Retainage This Period (%)' column.
- In the Total Retainage Released column, enter the total amount of work retainage being requested for release on the line item.
- Choose from these options for entering materials retainage:
- Materials Retainage ($). Enter a currency amount for the material retainage that you are requesting to be released this period. The value that appears here is based on your entries in the New Materials Stored and Previous Materials Stored columns. An entry in this cell lets Procore automatically calculate the percentage value in the 'Materials Retainage This Period (%)' column.
OR - Materials Retainage (%). Enter a percentage amount for the material retainage that you are requesting to be released this period. The value that appears here is based on your entries in the New Materials Stored and Previous Materials Stored columns. An entry in this cell lets Procore automatically calculate the percentage value in the 'Materials Retainage This Period (%)' column.
- Materials Retainage ($). Enter a currency amount for the material retainage that you are requesting to be released this period. The value that appears here is based on your entries in the New Materials Stored and Previous Materials Stored columns. An entry in this cell lets Procore automatically calculate the percentage value in the 'Materials Retainage This Period (%)' column.
- In the Total Retainage column, Procore calculates the sum of the 'Work Retainage This Period ($)' amount plus the 'Materials Retainage ($)' amount to represent the total retainage amount on the invoice.
Add Attachments
- Scroll to the 'Attachments' section.
- Choose from these options:
- Click the Attach Files button. This opens the Attach Files dialog box, where you can upload files from your computer. Click the Attach button when finished.
OR - Use a drag-and-drop operation to move the files from your computer or network into the 'Attachments area'.
- Click the Attach Files button. This opens the Attach Files dialog box, where you can upload files from your computer. Click the Attach button when finished.
Save the Invoice
Click the Save button at the bottom of the 'New Invoice' page.
Note: If workflows are turned on for subcontractor invoices, you can also choose 'Save as Draft' to save your work and stay in the same workflow step.
Send an Invoice with DocuSign©
Optional: If your project team wants to collect signatures on your invoices using the Procore + DocuSign© integration, click the Send with DocuSign© button at the top of the page. To use this button, the DocuSign© integration must be enabled on the project (see How do I enable the DocuSign® Integration?) and the invoice must be in the Approved, Approved as Noted, or Pending Approval status. To learn more about the DocuSign© integration and preparing envelopes for signature, see DocuSign®.