1-866-477-6267 (toll-free)
Support Home > Products > Procore > Procore User Guide > Project Level > Submittals > Tutorials > Create a Submittal

Create a Submittal

Objective

To create a submittal for a project using the project's Submittals tool.

Background

In the construction industry, a submittal is written and/or physical information provided by subcontractors to the general contractor and then to the design team for approval of equipment, materials, etc. before they are fabricated and delivered to the project. Submittals can be presented in various formats, such as shop drawings, cut sheets on equipment, and material samples. Submittals are required primarily for the architect and engineer to verify that the correct products and quantities will be installed on the project in compliance with the design documents/contract documents. 

In Procore, a submittal manager is the person responsible for overseeing a submittal throughout its lifecycle. If you create a submittal and have 'Standard' or 'Admin' level permission to the Submittals tool, your name appears as the 'Submittal Manager' by default. However, users with 'Admin' level permission to the Submittals tool have the ability to assign the submittal manager role to any Procore user who has been granted 'Standard' or 'Admin' level permission to the Submittals tool (Note: Users with 'Standard' permission do not have permission to change the submittal manager). The 'Submittal Manager' field lets you change ownership of a submittal, when the person who created a submittal (or that submittal's current manager) is no longer a member of the project team.

Although every company and project may have its specific process, it is common for the project manager or engineer to be responsible for acting as the submittal manager. First, the submittal manager will create the submittal. Next, the subcontractor provides the required documentation for the submittal. Then, when the required documentation is in place, the submittal is sent to the appropriate members of the design team for review and approval.

Things to Consider

Steps

  1. Navigate to the project's Submittals tool.
    This reveals the Submittals page. 
  2. In the right pane, click Create Submittal.



    This reveals the New Submittal page.
  3. Create the new submittal by following the steps in these tasks:

Add General Information

  1. In the New Submittal page, complete the data entry in the General tab as follows:


     
    • Title. The descriptive name that best summarizes the information in the submittal. 

    • Spec Section. The appropriate section from your project's specifications book (a.k.a., spec book). See Where do the selections in the 'Spec Sections' drop-down list in the Submittals tool come from?

    • Number & Revision. The submittal number and its revision number. See How are submittals numbered in Procore?

      Note: If you attempt to create a submittal with a duplicate number, a the following message appears. It is recommended that you click Cancel and then assign the submittal the next available number. If you click OK, the system will permit you to create a submittal with a duplicate number.


       
    • Submittal Package. The submittal package that contains the submittal. In Procore, adding submittals to a package is optional. The decision to add submittals to a submittal package is based on your project's requirements, which is determined by your company's or project's management team. For instructions, see Create a Submittal Package.

    • Status. The current status of the submittal. Only a user with 'Admin' level permission to the Submittals tool can change a submittal's status. See What are the default submittal statuses in Procore?




    •  
    • Responsible Contractor. The company name of the contractor/subcontractor that is responsible for completing the work specified on the submittal. 

    • Received From. The contact for the responsible contractor who provided the submittal information to the project team. 

    • Submit By. The date by which a contractor/subcontractor must submit all relevant documentation (i.e., documents, drawings, manuals, plans, and so on) for the submittal to the project's design team for review.

    • Issue Date. The date the contractor/subcontractor submitted the submittal items (i.e., documents, plans, and so on) to your project team for the review process. 

    • Received Date. The date that the submittal information was received from the contractor/subcontractor responsible for the performing work associated with the submittal.

    • Final Due Date. The due date by which all approvers on the submittal workflow must submit a response.

      Notes: When the 'Final Due Date' occurs, the system sends an automated email notification to notify users that the submittal is overdue. If your system is configured to use sequential approval, the notification goes to the Submittal Manager and the Ball in Court person on the approval workflow. If your system is configured to use parallel approval, the notification goes to the Submittal Manager and members of the approval workflow).
    • Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.

    • Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.



    •  
    • Cost Code. The cost code for the submittal. See What are Procore's Default Cost Codes?

    • Submittal Manager. The name of the submittal manager. This is the person who is responsible for overseeing the submittal throughout its lifecycle in Procore. Each submittal can have a different submittal manager or your project team can configure a 'Default Submittal Manager' for all of your submittals. See What is the 'Submittal Manager' role?

    • Type. The information type associated with the submittal. The default type selections in Procore include: Document, Pay Request, Payroll, Plans, Prints, Product Information, Product Manual, Sample, Shop Drawing, Specification, or Other. Types cannot be customized in Procore.

    • Private. The privacy settings for the submittal. When marked private it is only visible to 'Admin' on the Submittals tool, members of the submittal workflow, and members of the Distribution list on the submittal. See Mark a Submittal as Private.

    • Location. The location at the job site for the submittal. This can be an existing location from the Location list or a tiered location. See Add Tiered Locations to a Project

    • Linked Drawings. Renderings stored in the project's Drawings tool that are linked to the submittal. See Link Related Items on a Drawing.

    • Description. Informative details, notes, and/or actions that describe the submittal. 

    • Attachments. Attach any relevant files. You have these options:

      • Click Attach File(s) and then choose the appropriate option from the shortcut menu that appears.
        OR
      • Use a drag-and-drop operation to move files from your computer into the grey Drag and Drop File(s) box.

back to steps

Calculate Submittal Schedule Information (If Enabled)

Submittal Schedule Calculations is an optional feature that must be switched ON by Procore. See Request to Enable Submittal Schedule Calculations. When enabled, the Submittals tool will analyze your entries in the 'Required On-Site Date', 'Lead Time', 'Design Team Review Time', and 'Internal Review Time'fields to automatically calculate the 'Due Date' for approvers on the submittal workflow. It also automatically populates the 'Planned Return Date', 'Planned Internal Review Completed Date', and 'Planned Submit By Date' fields.

  1. Follow the steps in Create a Submittal
    This reveals the New Submittal page.
  2. Scroll down to the Submittal Schedule Information area. 
  3. Set the following information:
    1. Design Team Review Time. The number of days allotted for the design team's review on the submittal.

      Note: If you enter 7, the system subtracts '7' calendar days (NOT business days) from the Planned Return Date to automatically populate the date entry for the Planned Internal Review Completed Date.
    2. Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.

      Note: If you enter 10, the system subtracts '10' calendar days (i.e., NOT business days) from the Required On-Site Date to automatically populate the date entry for the Planned Return Date.
    3. Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.

    4. Internal Review Time. The number of calendar days (NOT business days) that your project's design team requires to ensure the submittal is properly reviewed.

      Note: If you enter 5, the system subtracts '5' calendar days from the Planned Internal Review Completed Date to automatically populate the date entry for the Planned Submit by Date.
      This illustration shows you an example of these entries and calculations.



      Now, when setting due dates for members of the submittal workflow, the due dates will be reflected in the workflow.

back to steps

Update the Delivery Information


 

  • Anticipated Delivery Date
    View the date displaying in the Anticipated Delivery Date. This is the date between the 'Lead Time' and when the submittal was distributed, and it will not populate upon the creation of the submittal. This date is calculated by Procore once the submittal has been distributed. See Distribute a Submittal.​​
  • Schedule Task
    If you have enabled the Schedule tool on the project and integrated an Asta PowerprojectMicrosoft Project, or Oracle Primavera schedule with Procore, you are permitted to select a project task from the Schedule Task drop-down list when you have a user account that has been granted 'Read-Only' level permission or higher on the Schedule tool. This is for reference only.
  • Confirmed Delivery Date
    Select the date the subcontractor or supplier confirmed the freight would arrive using the Confirmed Delivery Date calendar. 
  • Actual Delivery Date
    Select the date the material arrived on site using the Actual Delivery Date calendar. Typically, this value is updated by the project superintendent. 

back to steps

Create the Distribution List


 

  • Select one or more individuals using the Select A Person drop-down menu.
    The users on this list will receive email updates about the submittal. ​They are not approvers and they are not required to approve/reject a submittal. 
  • If you want to remove someone from the list, click the red X next to their name.

back to steps

Add Reviewers to the Submittal Workflow

Use the steps below when your project is configured to use submittal workflow (this is the default setting), submittals will be reviewed by the contacts named here using either the sequential approval (default) or parallel approval process. 

  1. In the new submittal page, scroll down to the Submittal Workflow area.
  2. In the Start Typing to Search People box, choose the desired reviewer. 
  3. In the Role drop-down list, select the 'Approver' or 'Submitter' role.
    Keep these points in mind:
    • To be designated as an approver, the person must exist in the Project level Directory tool (see Add a Person to the Project Directory) and must also be granted 'Admin' or 'Standard' level permissions to the Submittals too (see Set User Permissions for the Submittals Tool).
    • If you are a user with 'Standard' level permissions to the Submittals tool, you can only add reviewers with 'Admin' level permissions to the workflow.
    • If you are a user with 'Admin' level permissions to the Submittals tool, you can add reviewers with either 'Admin' or 'Standard' level permissions to the workflow. 
      (Note: If your company is a general contractor or construction management firm and you plan to add a Submitter to the submittal, Procore recommends that you always designate a Submittal Manager as the first reviewer in the submittal's sequential approval workflow. Then gives the Submittal Manager an opportunity to ensure the submittal is thoroughly reviewed by your internal stakeholder before it is sent to the subsequent reviewers (i.e., the design team) on the submittal workflow). 
  4. Use the calendar control to select a due date. Each 'Approver' must submit their response by the Final Due Date. 
  5. Click Add. 
  6. Repeat these steps to add another reviewer to the workflow. 

Update and Send the Submittal for Review

When finished with the steps above, choose one of these options:

  • To save your changes without sending an email to reviewers and distribution list members, click Create
    OR
  • To save your changes and to send an email notification to alert the reviewers on the workflow and to alert the members of the distribution list, click Create & Send Emails.
You must to post a comment.
Last modified
14:23, 21 Sep 2017

Tags

Classifications

This page has no classifications.