The Equipment tool helps you manage your company's equipment for your job sites. Whether owned or rented, Procore's Equipment tool ensures all machines are optimally used and effectively managed from arrival to departure.
This guide walks you through how to use Equipment in your project's Timesheets, T&M Tickets, and Budget.
After Equipment is created in your company's Equipment tool, you can add or remove equipment from your project. Equipment can be used in Inspections, Timesheets, T&M Tickets, and your Budget.
The Equipment tool must be enabled for your project. See Add and Remove Project Tools.
If you have existing integrations for a project that depend on equipment listed in the Project Settings of the project Admin tool, Procore recommends NOT enabling Equipment tool at this time.
Enabling the Equipment tool on a project disables existing third party integrations for that project that rely on the equipment listed in the in the project's Admin tool.
Navigate to the project's Equipment tool.
Click Add and select Add from Company Register.
If an equipment record doesn't exist, you can also create one. See Create an Equipment Record in the Project's Equipment Tool.
Mark the checkboxes for the equipment you want to add.
Click the Add.
Removing equipment from a project makes it unavailable in the project's drop-down menus.
Navigate to the project's Equipment tool.
Remove equipment.
Remove Inline
Hover over the equipment record and click the remove
icon.
Click Remove to confirm.
Bulk Remove
Mark the checkboxes for the equipment you want to remove.
Click Remove from Project.
Click Remove to confirm.
After Equipment is created in your company's Equipment tool, you can add or remove equipment from your project. Equipment can be used in Inspections, Timesheets, and your Budget.
To set the current project to show where equipment is onsite in the company's Equipment tool.
You can assign equipment to multiple projects and mark its current project to see where the equipment is onsite when viewing the company's Equipment register.

To see all projects equipment is assigned to, see View Equipment Project Assignments.
After you check in equipment from the project, the following is updated in Procore:
The equipment is added to your project's Equipment tool.
The project is set as the 'Current Project' to show where equipment is onsite in the company's Equipment tool.
When scanning the QR Code, the GPS location of your mobile device is used to update the location of the equipment if Location Services are enabled.
Navigate to the Equipment tool using the Procore app on an iOS mobile device.
Tap the equipment record to view details.
OR
Tap the QR code
icon. Then point your camera toward the QR code to open the equipment details page.
If the equipment has not yet been added to your project, tap Add to Project.
Move the 'Onsite' toggle
to the ON position to mark it as 'onsite'.
After you check in equipment from the project, the following is updated in Procore:
The equipment is added to your project's Equipment tool.
The project is set as the 'Current Project' to show where equipment is onsite in the company's Equipment tool.
When scanning the QR Code, the GPS location of your mobile device is used to update the location of the equipment if Location Services are enabled.
Navigate to the Equipment tool using the Procore app on an Android mobile device.
Tap the equipment record to view details.
OR
Tap the QR code
icon. Then point your camera toward the QR code to open the equipment details page.
If the equipment has not yet been added to your project, tap Add to Project.
Move the 'Onsite' toggle
to the ON position to mark it as 'onsite'.

|
Video content may not accurately reflect the current state of the system, and/or it may be out of date. |

With the bulk create feature, you can quickly create multiple inspections with identical details to save time.
|
|
To save time, use the TAB and ENTER keys on your keyboard to switch between sections and buttons.
You can configure what items are created with the quick create
icon, see Configure Quick Create Settings.
You can create an inspection from the following places:
If required fields are empty, click Fix Errors to go to the first empty field. Click Next Field or Previous Field to view other empty required fields.
After the required fields have been entered, you will be able to create or save the form.
Additional Information:
This action can also be performed while an active network connection is not available on your mobile device (offline mode). Tasks performed in offline mode will be synced with Procore after a network connection has been reestablished.
You can configure what items are created with the quick create
icon, see Configure Quick Create Settings.
You can create an inspection from the following places:
If required fields are empty, click Fix Errors to go to the first empty field. Click Next Field or Previous Field to view other empty required fields.
After the required fields have been entered, you will be able to create or save the form.
This asset or item can be viewed or edited in offline mode if it was previously viewed and cached on your mobile device. Tasks performed in offline mode sync with Procore once a network connection is reestablished.

|
Video content may not accurately reflect the current state of the system, and/or it may be out of date. |
Add additional information.
To sync Equipment Timesheets with Daily Log entries, the following must be true:
The configurable fieldset for Daily Log Equipment Entries must match the Equipment fieldset for Timesheets.
The Daily Log must be open and not marked as 'Complete'.
Users must have permissions to create a timecard entry.
Users must have permissions to create an Equipment Daily Log Entry.
Navigate to the project's Daily Log tool.
Scroll to the Equipment section.
Enter the following information:
Equipment Name. Select the equipment from the drop-down list.
Hours Operating. Enter the number of hours the equipment was active.
Hours Idle. Enter the number of hours the equipment was idle.
Cost Code. Select the cost code associated with the entry.
Location. Select the location from the drop-down list.
Inspected. Mark the checkbox if the equipment was inspected.
Inspection Time. Enter what time the equipment was inspected.
Comments. Add any comments.
Click Create.
If required fields are empty, click Fix Errors to go to the first empty field. Click Next Field or Previous Field to view other empty required fields.
After the required fields have been entered, you will be able to create or save the form.
Manage any equipment added to this section by viewing the Equipment list on the Equipment page of the Admin tool.
Note: Requires 'Admin' permissions on the Admin tool.
Equipment Name: Tap the Equipment Name field. Enter the name of the equipment.
# Hours Operating: Enter the number of hours the equipment was operating.
# Hours Idle: Enter the number of hours the equipment was idle.
Cost Code: Tap the Cost Code field. Select from the drop-down menu the cost code associated with the entry.
Location: Select a location from the menu. Tap a tiered location to pull up any sub locations. Tap Add to add that location. You may also tap QR in the top right to scan a location's QR code if a team member has Generated Location QR Codes for the jobsite.
Inspected: By default, the Inspected button will be set to 'No.' Toggle the Inspected button to 'Yes' if the equipment was inspected that day.
Inspection Time: Enter the time the equipment was inspected by selecting the hour and minutes from the menu.
Attachments: Tap on the following options to add photo or file attachments to the entry:
Notes: Enter any notes that may describe the entry.
To configure what items are created with the quick create
icon, see Configure Quick Create Settings.
Open the Procore app on an iOS mobile device and select a project.
Note: This loads the Tools screen for the project.
Tap the quick create
icon and select Equipment Entry.
OR
Tap the Daily Log tool and tap Equipment. Then tap the create
icon.
Tap into the following fields to enter information.
Equipment Name: Tap and select the equipment from the drop-down list.
Hours Operating: Tap and enter the number of hours the equipment was active.
Hours Idle: Tap and enter the number of hours the equipment was idle.
Cost Code: Tap and select the cost code associated with the entry.
Location: Tap and select the location from the drop-down list.
Inspected: Tap to mark the checkbox if the equipment was inspected.
Inspection Time: Tap and enter what time the equipment was inspected.
Comments: Tap and add any comments.
Tap Create.
Click Fix Errors to go to the first empty field, if the required fields are empty.
Click Next Field or Previous Field to view other empty required fields.
After the required fields have been entered, you will be able to create or save the form.
To create a T&M ticket.
You can create a new T&M ticket to quickly document out-of-scope work when it’s requested in the field using the steps below or your mobile device. Your ticket is immediately visible to your office. You can also request stakeholder signatures and log the labor, equipment, and materials used.
To appear in the list for the 'Ordered by' and 'Signee' fields, the person must have a user account in the project's Directory tool. See Add a User Account to the Project Directory.
To appear in Labor category, people must be listed as employees or workers for your company. See Add Someone as an Employee of Your Company or Add a Worker.
To appear in list for the 'Company' field, the company must have a record in the Project Directory. See Add a Company to the Project Directory.
T&M Tickets are automatically set to the 'In Progress' status when created, but will update to the 'Ready for Review' status when the ticket has been signed by the Company Signee. When the Customer Signee has signed and verified the ticket, the status will update to 'Field Verified'.
To create a Time and Materials ticket in the T&M Tickets tool using the Procore app on an iOS mobile device.
You can configure what items are created with the quick create
icon, see Configure Quick Create Settings.
To create a T&M ticket using the Procore app on an Android mobile device.
You can configure what items are created with the quick create
icon, see Configure Quick Create Settings.
In Procore, timecards and timecard entries are used to log the number of hours employees and workers spend doing work on a construction project. Each day, you will create a new daily timesheet. A daily timesheet contains the individual timecard entries submitted by your employees and workers for a specific date. By default, Procore's timecard entries track the work's cost code, work location, number of hours worked, time type (for example, regular or overtime), and mark whether or not the entry's hours are billable. A tool administrator also has the option to configure your project's timesheets to capture timekeeping data such as classifications and sub-jobs.
You can also use these options to create a new daily timesheet:
To create a timesheet using the Procore app on an iOS mobile device.
This action can be performed in offline mode. Tasks performed in offline mode sync with Procore once a network connection is reestablished.
|
|
to the ON to automatically apply Overtime Rules. See Configure Overtime Rules for Timesheets.
OR
To create a timesheet on your Android mobile device.
In Procore, timecards and timecard entries are used to log the number of hours employees and workers spend doing work on a construction project. Each day, you will create a new daily timesheet. A daily timesheet contains the individual timecard entries submitted by your employees and workers for a specific date. By default, Procore's timecard entries track the work's cost code, work location, number of hours worked, time type (for example, regular or overtime), and mark whether or not the entry's hours are billable. A tool administrator also has the option to configure your project's timesheets to capture timekeeping data such as classifications and sub-jobs.
to the ON to automatically apply Overtime Rules. See Configure Overtime Rules for Timesheets.
OR
Type: Tap to select the type of time being entered.
Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.
To see equipment hours in your budget, you must create a budget view with the 'Equipment Timecard Hours' column. We recommend using the Labor Productivity Cost view as it contains the most relevant columns, and adding Equipment Timecard Hours to that view.
The 'Procore Labor Productivity Cost' budget view provides project teams with the ability to include production quantities on the project's budget. See What are 'production quantities'? Building off the Real-Time Labor Costing feature, the 'Procore Labor Productivity Cost' budget view is designed to provide self-performing and specialty contractors with the ability to gain greater insight into your project's production rates to make better decisions that maximize profit margins. With this release, you can:
By default, Procore provides its users with a standard 'Procore Labor Productivity Cost' budget view, which is available to your company's Procore Administrator in the Company level Admin tool.
Procore Labor Productivity Cost Budget View in the Budget Tool
The illustration below shows you the recommended layout for the 'Procore Labor Productivity Cost' budget view, as it will look when applied to your project's Budget tool.

Default Columns
The following table details the default columns provided with the 'Procore Labor Productivity Cost' budget view. In the Description column, the following symbols represent the operator for a calculation:
| Column Name | Column Type | Column Format | Column Description | Column Configuration |
|---|---|---|---|---|
| Revised Budget | Calculated | Currency | Shows the Original Budget amount, plus the Budget Change amount, plus the Approved COs amount. | Original Budget Add (+) Budget Changes Add (+) Approved COs |
| Direct Costs | Source | Currency | Shows the Direct Costs amount. | Source Category: Direct Costs Source: Direct Costs Source Filtering: Status = Pending, Revise and Resubmit, Approved |
| Direct Costs Unit Cost | Source | Number | Shows the actual cost per unit for direct costs. | Direct Costs Divide (/) Direct Costs Unit Qty |
| % Budget Complete | Calculated | Percent | Shows how much of the current budget amount for the budget line item is estimated to be used based on the real-time labor hours and actual labor cost. | Estimated Cost w/ Timesheet Hours Divide (/) Revised Budget |
| Projected Labor Cost at Completion | Calculated | Currency | Shows the projected labor cost at completion for the budget line item. | Projected Hours at Completion Multiply (*) Direct Costs Unit Cost |
| Projected Labor Cost Over/Under | Calculated | Current | Shows the Revised Budget minus the Projected Labor Cost at Completion. | Revised Budget Subtract (-) Project Labor Cost at Completion |
| Revised Budgeted Unit Qty | Calculated | Number | Shows the Budget Production Qty plus the Approved COs Production Qty. | Budget Unit Qty Add (+) Approved CO Units |
| Budget UOM | Standard | n/a | Shows the Unit of Measure (UOM) for the budget line item. | n/a |
| Timesheet Hours 1 | Source | Number | Shows all Timecard Entry Hours. You can optionally apply Status filters to narrow the data in the view. | Source Category: Timecard Entry Hours Source: Timecard Entry Hours Filtering: None |
| % Hours Used | Calculated | Percent | Shows how much of the current budget unit qty (labor hours) have been used based on time submitted in Procore. | Timesheet Hours Divide (/) Revised Budget Unit Qty |
| Earned Hours | Calculated | Number | Shows the number of labor hours earned (merited) based on the work produced to date for that cost code. |
Revised Budget Unit Quantity |
| Projected Hours at Completion | Calculated | Number | Shows the estimated labor hours needed to complete production for the cost code based on the work produced to date. | Timesheet Hours Divide (/) % Complete Production |
| % Complete Production | Calculated | Percent | Shows the percentage of the production quantity has been installed to date of the current budgeted production quantity for the cost code. | Actual Qty Installed Divide (/) Revised Budgeted Production Qty |
| Production UOM | Source | n/a | Shows the UOM for the budgeted production quantity (i.e., for the cost code on the line item). | Source Category: Production UOM Source: Budgeted Production UOM Source Filtering: n/a |
| Revised Budgeted Production Rate | Calculated | Number | Shows the actual budgeted production rate based on labor hours and installed quantities to date. | Revised Budgeted Production Qty Divide (/) Revised Budget Unit Qty |
| Actual Production Rate | Calculated | Number | Shows the actual budgeted production rate based on labor hours and installed quantities to date. | Actual Qty Installed Divide (/) Timesheet Hours |
| Variance Production Rate | Calculated | Number | Shows the difference between the current budgeted production rate and the actual production rate. A positive number indicates you are performing faster than expected. A negative number indicates you are performing slower than expected. | Actual Production Rate Subtract (-) Revised Budgeted Production Rate |
1 The 'Labor Productivity Cost' budget view is only available to customers using Procore's Resource Tracking tools. However, the 'Timesheet Hours' column can be added to other budget views. To learn how to add the column, see Can we import our third-party timecard entries to work with the 'Timesheet Hours' column in Procore's Budget tool?
Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.



Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.
For companies using the
ERP Integrations tool:
If your company account is using the ERP Integrations tool, Procore automatically provides you with a budget view for your Integrated ERP System. See Which ERP integrations are supported by Procore? for details about your specific ERP connector.
Any custom budget views that you create for an ERP Integration must contain all of the required ERP data columns. This ensures that Procore can send the required budget data to the company's ERP Integrations tool for acceptance for export to the integrated ERP system by an Accounting Approver. See Send a Budget to ERP Integrations for Accounting Acceptance.
| Steps from the Configure Columns window… | Settings |
|---|---|
|
![]() |
Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.
For companies using the
ERP Integrations tool:
If your company account is using the ERP Integrations tool, Procore automatically provides you with a budget view for your Integrated ERP System. See Which ERP integrations are supported by Procore? for details about your specific ERP connector.
Any custom budget views that you create for an ERP Integration must contain all of the required ERP data columns. This ensures that Procore can send the required budget data to the company's ERP Integrations tool for acceptance for export to the integrated ERP system by an Accounting Approver. See Send a Budget to ERP Integrations for Accounting Acceptance.
After closing the Configure Columns window, the system returns you to the new budget view's window. Under Column Configuration, you can get an idea of how your budget view will look in Procore by selecting a project from the Preview with Project drop-down list.
Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.
For companies using the
ERP Integrations tool:
If your company account is using the ERP Integrations tool, Procore automatically provides you with a budget view for your Integrated ERP System. See Which ERP integrations are supported by Procore? for details about your specific ERP connector.
Any custom budget views that you create for an ERP Integration must contain all of the required ERP data columns. This ensures that Procore can send the required budget data to the company's ERP Integrations tool for acceptance for export to the integrated ERP system by an Accounting Approver. See Send a Budget to ERP Integrations for Accounting Acceptance.
After previewing your budget view and determining that it suits your business needs, you can assign it one or more Procore projects.
Click the Assign to Projects drop-down list.

Place a checkmark in the box next to one or more of the following options:
All Projects Selected. This assigns the new budget view all of your Procore projects.
All Projects Using ERP Direct Costs. This assigns the new budget view to projects using the ERP Direct Costs budget view.
All Projects Using Procore Direct Costs. This assigns the new budget view to projects using the project level Direct Costs tool.
[Individual Projects]. This assigns the new budget view to only the project(s) that you select.
Click Done.
Required User Permissions:
'Admin' on the Company Admin tool.
Additional Information:
To set up a budget view for real-time labor productivity, see Resource Tracking and Project Financials: Setup Guide.
To set up a labor productivity cost budget view, see Set Up the Procore Labor Productivity Cost Budget View.
Any user with 'Read Only' permission or higher on the Budget tool has access permission to apply the view to a project's budget. See Apply the View, Snapshot, Group, and Filter Options on a Budget or Forecasting View.
For companies using the
ERP Integrations tool:
If your company account is using the ERP Integrations tool, Procore automatically provides you with a budget view for your Integrated ERP System. See Which ERP integrations are supported by Procore? for details about your specific ERP connector.
Any custom budget views that you create for an ERP Integration must contain all of the required ERP data columns. This ensures that Procore can send the required budget data to the company's ERP Integrations tool for acceptance for export to the integrated ERP system by an Accounting Approver. See Send a Budget to ERP Integrations for Accounting Acceptance.
Navigate to the project's Budget tool. Then click the Budget, Budget Details, or Project Snapshot Status tab and select an option from the View menu. To add views to this menu, see Assign a Budget View to a Project.

Company Equipment Required User Permissions
Project Equipment Required User Permissions
QR Codes must be scanned with QR reader for the Equipment tool in the Procore mobile app:
QR Codes must be scanned with QR reader for the Equipment tool in the Procore mobile app.
You must give the Procore mobile app permission to access the camera on your mobile device.
If Location Services are enabled on your mobile device, the GPS location of your mobile device is used to update the location of the equipment.
Navigate to the Equipment tool using the Procore app on an iOS mobile device.
Tap the QR code
icon.
Point your camera toward the QR code to automatically scan it and show the equipment details.
Optional: Continue your workflow by taking the following actions:
QR Codes must be scanned with QR reader for the Equipment tool in the Procore mobile app.
You must give the Procore mobile app permission to access the camera on your mobile device.
If Location Services are enabled on your mobile device, the GPS location of your mobile device is used to update the location of the equipment.
Navigate to the Equipment tool using the Procore app on an Android mobile device.
Tap the QR code
icon.
Point your camera toward the QR code to scan it and show the equipment details.
Optional: Continue your workflow by taking the following actions: