Create Scheduled Work Entries
Objective
To create Scheduled Work entries in the project's Daily Log tool.
Background
Things to Consider
- Required User Permissions:
- To create entries:
- 'Standard' or 'Admin' level permissions on the project's Daily Log tool.
- To create pending entries as a collaborator:
- 'Read Only' or 'Standard' permissions to the Daily Log tool with the 'Collaborator Entry Only' granular permission enabled on your permissions template. See Create Daily Log Entries as a Collaborator.
- To create entries:
- Additional Information:
- Information such as the resource and task name can be carried over to the Scheduled Work log from the project's schedule. If you want this information to be populated automatically, ensure the following prerequisites are met:
- A schedule file, such as a Microsoft Project file, must be uploaded to the project's Schedule tool. See Upload a Project Schedule File to Procore's Web Application.
- The schedule file must include resource assignments on the project's tasks. Refer to your schedule program's support resources for specific instructions.
- Information such as the resource and task name can be carried over to the Scheduled Work log from the project's schedule. If you want this information to be populated automatically, ensure the following prerequisites are met:
Steps
- Navigate to the project's Daily Log tool.
- Scroll to the Scheduled Work section.
- Fill out the following information:
- Click Create.