Add Line Items to a Schedule of Values on a Prime Contract
Objective
To add line items to a Schedule of Values (SOV) on a prime contract.
Background
An SOV is an itemized list of all the work items on a project. Each line item shows the work item's cost.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Prime Contracts tool.
Note: To limit subcontractors (and other users in other roles) from viewing your contract data, configure the granular permissions feature when applying permission templates. See Manage Project Permissions Templates and Grant Granular Permissions in a Permission Template.
- 'Admin' level permissions on the project's Prime Contracts tool.
- Additional Information:
- Other methods for adding SOV line items to a contract include:
- Import a Prime Contract SOV from a CSV File
- Create a Prime Contract SOV from the Project Budget
Note: Not recommended for projects with multiple prime contracts. See Are there any system limitations when creating multiple prime contracts?
- Other methods for adding SOV line items to a contract include:
Prerequisites
- Create Prime Contracts
- Set the accounting method on the contract. See Edit the Advanced Settings on a Prime Contract.
Steps
- Navigate to the project's Prime Contracts tool.
- Locate the contract to update and click its Number link.
- Click the Schedule of Values tab.
- Click Add Line.
- Complete the data entry as follows:
- Budget Code
Select a budget code or click Create Budget Code. See What is a budget code in Procore's WBS? - Description
Enter a description for the line item. For example, type: Monthly Service Fee - Qty
Enter the number of units. - UOM
Select a Unit of Measure (UOM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a Unit of Measure to the Unit of Measure Master List. - Unit Cost
Enter the cost per unit in this box. You'll notice that the value in this column contains four (4) decimal points (for example, $0.0000) to allow you to enter the specific value required to calculate accurate pricing.Example
If you are buying 50,000 units for $1,006,625.00, you would enter a unit price of $20.1325. - Amount
The system automatically calculates the subtotal for you, based on the Qty, UOM, and Unit Cost entries.
- Budget Code
- Repeat the above steps for all line items.
Tip
Want to arrange the line items on your schedule of values into groups? Click the Add Group menu and select the desired grouping options. The default options include Cost Code, Cost Type, Sub Job (if enabled), as well as any custom segments that have been added for your company or project. See What are Segments and Segment Items. - Choose one of these options:
- Click Save
OR - Click Save & Email.
- Click Save