Add Financial Markup to Prime Contract Change Orders
In Beta
Instructions for the Advanced Financial Markup beta can be read in the following article: (Beta) Add Financial Markup to Prime Contract Change Orders.Objective
To add financial markup to a change order.
Background
In Procore, the term financial markup is used to refer to an increase that is applied to the cost of a product or service in order to arrive at its final cost. You can set two (2) types of markup on change order line items.
- Horizontal Markup. A horizontal markup calculates the markup amount on an individual line item.
- Vertical Markup. A vertical markup calculates the markup amount as a subtotal on all of the line items on a change order.
In addition, you can associate your financial markup settings to cost codes, categories, and sub-jobs. This ensures that the financial markup on your project's change orders is reflected accurately on your project's budget.
Things to Consider
- Required User Permissions:
- To add financial markup, 'Admin' level permissions on the project's Prime Contracts tool.
- To view financial markup on the change order's Schedule of Values (SOV), 'Standard' level permission on both the project's Change Orders and Prime Contracts tools.
- Additional Information:
- If you do NOT select a cost code or cost type for the financial markup, it will appear as:
- Cost Code=None
- Cost Type=None
- Division=None
- If you do NOT select a cost code or cost type for the financial markup, it will appear as:
- For companies using the ERP Integrations tool: Show/Hide
- Some ERP integrations do NOT support the sync of horizoontal markups, vertical markups, or both. See Things to Know About your ERP Integration for details.
Prerequisites
- Add the Budget tool to your project. See Add and Remove Project Tools.
- Your company's Procore Administrator must do the following:
- Complete the steps in Create Your Company's Default Work Breakdown Structure and Enable Sub Jobs for WBS.
- Complete the steps in Create Your Project's Work Breakdown Structure and Add Sub Jobs to a Project.
- Enable Financial Markup. See Edit the Advanced Settings on a Prime Contract.
- Create at least one (1) item. See Create Prime Contracts.
Steps
- Navigate to the project's Prime Contracts tool.
- Locate the prime contract to work with. Then click its Number link.
- Click Financial Markup.
Note
This tab is only available if it has been enabled in the appropriate tool's Advanced Settings tab. - Under Financial Markup Settings, you have these options:
- New Horizontal Markup. Click this button to display the markup in the same row as the line items.
- New Vertical Markup. Click this button to display the markup below the line items.
Notes
- To learn about the differences between markup types, see What is the difference between horizontal and vertical financial markup?
- You can apply financial markup settings on a per-change order basis.
- Enter information in the Markup List as follows:
- Markup Name. Enter a name for the financial markup.
- Markup Percentage. Enter the percentage for the markup.
- Compounds Markup Above. Move the toggle to the right to compound your new markup. This setting is turned OFF by default.
- Under Maps To, do the following:
- Budget Code. Select the budget code that the markup percentage will be applied to. To learn more, see What is a budget code in Procore's WBS?
- Applies To. Choose the cost types that the markup percentage will be applied to. By default, Procore lists all of your existing cost types, so you can click the X on each cost type object to remove it. See What are Procore's default cost types? and Add Company Cost Types. If you want to remove one or more cost types, click the 'x' next to the desired selections.
- For companies using the ERP Integrations tool:
- ERP Prime Contract Item. Select the desired Schedule of Values (SOV) line item from the project’s Prime Contract. This ensures that the estimated value (the SOV value without vertical markup) and the revenue value (the SOV value with vertical markup) are synced to the line item that you specify in the integrated ERP system.
Notes
This field is only visible when:- Your company account has enabled the ERP Integrations tool.
- The ERP Integrations tool is configured to use either the Integration by Ryvit or Sage 300 CRE®.
- You are creating vertical markup on a prime contract change order.
- Export Markup to Estimate. Select this checkbox to enable the ability to sync financial markup on a prime contract to the cost estimate in ERP. This checkbox is only available to customers with the Sage 300 CRE® integration, Integration by Procore with Viewpoint® Spectrum®, or Integration by Ryvit with Viewpoint® Vista™ .
- ERP Prime Contract Item. Select the desired Schedule of Values (SOV) line item from the project’s Prime Contract. This ensures that the estimated value (the SOV value without vertical markup) and the revenue value (the SOV value with vertical markup) are synced to the line item that you specify in the integrated ERP system.
- Click Save.