Add a Line Item to a Commitment's Schedule of Values

Objective

To add a line item to a Schedule of Values (SOV) for a subcontract or purchase order in the Commitments tool to account for costs included in the commitment.

Background

schedule of values is a list of line items that details all of the agreed upon costs (e.g., labor, materials, and so on) on a project. Abbreviated as SOV, it itemizes the contract amount into individual pay items to show how the entire contract sum is allocated to all of the project's work. An SOV is also based on the project's approved budget and commonly used to determine progress payments to contractor(s).

Things to Consider

  • Required User Permission:
    • 'Admin' on the project's Commitments tool.
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  

    • In order to send the commitment to the ERP Integrations tool to be accepted for export by an accounting approver:
      • Integration by Ryvit. The commitment must have at least one (1) SOV line item with a Integration by Ryvit phase code. In addition, the cost code must be assigned to at least one (1) category. See Assign Default Cost Types To Integration by Ryvit Cost Codes). Important! When a commitment is exported to Integration by Ryvit, it must have a unique commitment number. Procore recommends that the numbering convention you set up for the Commitments tool is preceded by the Project Number and then uses the default numbering system. For example, if your Project Number is 001, your numbering system would be 001-001, 001-002, 001-003, and so on. 
      • QuickBooks®. The commitment must have at least one (1) SOV line item with a QuickBooks® cost code. The cost code does not need to be assigned to a category, because QuickBooks® does not support the category concept.
      • Sage 100 Contractor®. A commitment must have one (1) SOV line item with a Sage 100 Contractor® cost code. In addition, the cost code must be assigned to at least one (1) cost type. See Assign Default Cost Types To Cost Codes.
      • Sage 300 CRE®. The commitment must have at least one (1) SOV line item with a Sage 300 CRE® cost code. In addition, the cost code must be assigned to at least one (1) cost type. See Assign Default Cost Types To Cost Codes.
      • Viewpoint® Spectrum®. The commitment must have at least one (1) Schedule of Values (SOV) line item with a cost code from the Viewpoint® Spectrum® project. The cost code must be assigned to at least one (1) category. Category assignments must always be updated in Viewpoint® Spectrum®. 

Steps

  1. Navigate to the project's Commitments tool.
  2. Click the Summary or Detailed tab.
  3. Locate the purchase order or subcontract in the list. Then click Edit.
  4. Click Schedule of Values.
  5. Click Add Line.
  6. Follow the appropriate steps depending on whether your accounting method is Amount Based or Unit/Quantity Based:
     Note
    To edit your accounting method before adding SOV line items, see Edit the Advanced Settings Tab on a Commitment. For more information on accounting methods, see How do I set the accounting method for a commitment or prime contract?
    1. For Amount Based contracts
      1. Change Event Line Item
        If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event. 
      2. Budget Code
        Select a budget code from the or click Create Budget Code to create a new one. See What is a budget code?
      3. Description
        Enter a description for the line item. For example, type: Monthly Service Fee
      4. Amount
        Enter the amount of the cost.
      5. Billed to Date
        The system automatically calculates the amount billed on the commitment up to the current date.  
      6. Amount Remaining
        Enter the amount that has NOT been billed to the current date. 
      7. Tax Code
        Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
    2. For Unit/Quantity Based contracts
      1. Change Event Line Item
        If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event. 
      2. Budget Code
        Select a budget code from the or click Create Budget Code to create a new one. See What is a budget code?
      3. Description
        Enter a description for the line item. For example, type: Monthly Service Fee
      4. Qty
        Enter in the quantity of units.
      5. UOM
        Enter the Unit of Measure (UOM) in the list.
         Notes
      6. Unit Cost
        Enter the Unit Cost in the box provided.
      7. Amount
        The system automatically calculates the subtotal for you, based on the QtyUOM, and Unit Cost entries. 
      8. Billed to Date
        The system automatically calculates the amount billed on the commitment up to the current date. 
      9. Amount Remaining
        Enter the amount that has NOT been billed to the current date. 
      10. Tax Code
        Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
  7. Choose one of these options:
    • Save. Click this button to save your purchase order. 
      OR
    • Save & Email. Click this button if you are ready to forward the purchase order to the subcontractor.