How do I edit a project schedule in Procore?
Background
While some companies use Procore's Schedule tool to build detailed project timelines, other companies opt to integrate their own third-party software solutions (e.g.,Microsoft Project, Asta Powerproject, or Oracle Primavera). For customers using third-party tools, you can integrate an existing schedule with a project managed in Procore by uploading the project schedule into Procore so that all members in your project can view a read-only version of the project schedule.
Answer
You cannot edit an integrated project schedule directly in Procore. Instead, you must modify the schedule in your third-party software (e.g. Microsoft Project or Oracle Primavera) and then the revised schedule into Procore. See the following articles to learn how:
- Update an Integrated Microsoft Project Schedule
- Integrate a Primavera P6 Schedule using Procore Drive
- Integrate an Asta Powerproject Schedule Using Procore Drive
If you have built your calendar items by creating a calendar item in Procore, you can edit those items in Procore. See Edit a Calendar Item.