Update the Percent Complete for a Schedule Task (Android)
Objective
To update the Percent Complete field in the project's Schedule tool using an Android mobile device.
Things to Consider
- Required User Permissions:
    
- 'Admin' level permissions on the Project level Schedule tool.
OR - 'Read Only' or 'Standard' level permissions with the 'Update Task Completion Percentages' granular permission enabled on the permission template.
 
 - 'Admin' level permissions on the Project level Schedule tool.
 - Additional Information:
    
- Updating the percent complete on mobile does not update the percent complete in the native schedule file. See How do I get the percent complete updated in the native schedule file?
 - Percent Complete cannot be updated for Summary schedule tasks or Milestones.
 - Percent Complete for calendar items cannot be updated in the mobile application.
        
 
 
Prerequisites
- The setting for updating schedule tasks must be enabled on the Schedule tool's Configure Settings page. See How do I allow users to update the 'Percent Complete' field in the Schedule tool?.
 
Steps
- Navigate to the project's Schedule tool using an Android mobile device.
 - Tap the schedule task you want to update.
 - Tap Edit.

Note: Percent Complete cannot be updated for Summary schedule tasks or Milestones. - Enter the current Percent Complete for the task and tap Done.

Note: You can enter a numeric value from 0 to 100. The value you enter must be a whole number. - Tap Save.
 - The schedule task on the mobile device updates to show the amount you entered for Percent Complete.
Note: These changes are also shown in the Schedule tool on the web application.

 