(Beta) Edit Segment Items

 In Beta
This page details functionality that is not available in Procore's production environment. Access to the features documented here is limited to specific Procore customers who have signed the required agreement to participate in Procore's Work Breakdown Structure (WBS) Beta Program. The content on this page is for informational purposes only. All information and content on this page is subject to change without any prior notice. 

Objective

To add a segment items to a segment in your Company level Work Breakdown Structure (WBS)

Background

segment is a discrete category that an organization uses to break down its work into manageable components. A segment item is one of many distinct items in a segment. After creating a segment, you can add an unlimited number of segment items to it. You can also use the steps below to edit your custom segment items.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Company level Admin tool. 
  • Additional Information:
    • Any edits you make at the Company level are automatically reflected on all of your company's existing Procore projects.
  • Limitations:
    • You cannot edit the 'Code' field on a custom segment when it is being used on a project's budget code. 
    • In a flat segment, duplicate entries in the 'Code' field are NOT permitted. 
    • In a tiered segment, duplicate entries in the 'Code' field are NOT permitted when the segment items are children of the same parent segment. 
    • There are no character limits or other limitations on entries in the 'Description' field. 
  • For companies using the erp3 (1).png ERP Integrations tool: Show/Hide  
    • Custom Segments are NOT supported with the ERP Integrations tool.

Prerequisites

Steps

  1. Navigate to the Company level Admin tool. 
  2. Under 'Company Settings', click the Work Breakdown Structure link. 
  3. In the 'Segments' table, click the segment that you want to work with.

    wbs-segments-add-segment-item.png 
     Note
    For example, let's assume you created a custom segment named 'Phase' with segment items named 'Phase I', 'Phase II', and 'Phase III'  You want to rename the segment 'Stage' and its segment items 'Stage 1, Stage 2, and Stage 3.'
  4. In the 'Segment Item' table, do the following:

    wbs-add-segment-line-item.png
    • Code. Type over the existing entry with a unique alphanumeric code for the segment item. Then press the TAB key to move system focus to the 'Description' field. For example, enter: Stage
       Important
      If the custom segment item is being used on a project's budget code, you will NOT be able to change its 'Code' value. 
    • Description. Type of the existing entry with an updated description of the segment item. Then press the TAB key to save the new segment item to the list. A GREEN 'Success' banner appears to confirm that the update was saved. For example, enter: Stage 1, Stage 2, or Stage 3
  5. Repeat the steps above to change other segment items as needed.