Objective

To notify users of punch items that are assigned to them.

Things to Consider

  • Required User Permissions: 
    • 'Admin' permissions on the project's Punch List tool.
      Note: 'Read Only' level users cannot be assigned to a punch list list item.
    • 'Standard' permissions on the project's Punch List tool for users who are listed as Default Punch Item Managers in the Punch List configuration settings, see Configure Advance Settings: Punch List
  • Additional Information:
    • The punch list item must have already been created and saved before it can be sent.
    • Punch items must have an assignee in order to send the notification.
    • You can automatically send notifications to additional users when 'Item Sent to Assignees (Work Required)' is configured in Advanced Settings. See Configure Advance Settings: Punch List
    • Once an initial notification has been sent, selected Assignees will receive daily notifications of overdue items via email; email notifications will end after 45 days. 

Steps

Send all Punch List Items

To send all pending punch list items, follow the steps below:

  1. Navigate to your project's Punch List tool. ​​​​​
  2. Choose from the following options displayed in the banner:
    • Click Send All to send an email to assignees of new punch items, as well as any other users configured in Advanced Settings.
    • Click Send Mine to send only the punch list items you've created.
      Note: The 'Send All' and 'Send Mine' banners only show on the Punch List tool if the punch list item has an assignee. Additionally, the Send Mine button will only appear if there are punch list items that you created that have not yet been sent.
  3. Once you click Send, the 'Date Notified' column on the list page will update to reflect the current date (i.e. the day you sent the email). This allows you to record and track the date of notification.