Reorder Revisions of a Drawing

Objective

To reorder revisions of a drawing.

Background

By default, drawing revisions are ordered based on the 'Drawing Date' that is entered when uploading drawings. The revisions for a drawing can be reordered while reviewing drawings, but they can also be reorganized at any time on the drawing's General Information page.

Things to Consider​

  • Required User Permissions:
    • 'Admin' on the project's Drawings tool.
  • Prerequisites:

Steps

  1. Navigate to your project's Drawings tool.
  2. Select the drawing you want to reorder revisions for and click the info icon-info-wfp.png icon next to the drawing to view the drawing info.
  3. In the 'Versions' section, click and hold over the grip (⁞⁞) icon and use a drag-and-drop operation to arrange the revisions into a new order.

    reorder.png

    Note: The changes are saved automatically.