Skip to main content
Procore

Add Quantities to a Timesheet (iOS)

Also available on    

Objective

To add quantities to a timesheet that can then be tracked in the Production Quantity Report on an iOS mobile device.

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.
  • Installed production quantities refers to the actual amount installed on a project by a point in time.

Use the steps below to enter installed production quantities on a timesheet. One entered, they can then be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

  • Required User Permission:

    • 'Admin' level permission on the project's Timesheets tool.
      OR
    • 'Standard' level permission on the project's Timesheets tool AND creator of the timesheet.
  • Additional Information:

Steps            

Now that you have filled out your timesheet, perform the following actions before you submit:

  1. Tap Submit.
  2. Tap Submit and Add Quantities.

    2018-07-10_10-21-27.png

    Note: You will receive an error message if quantities have not been uploaded in the project. See Import Budgeted Production Quantities.
  3. Tap the Quantities field and enter the desired amount.
    Note: The data entered in the Budgeted Quantity import will pull in the Unit Of Measure and Percent Complete based off of cost code on this page.
  4. Click Submit.

 

  • Was this article helpful?