Set or Release Retainage on a Subcontractor Invoice
Back | Current Lesson - 13/23 | Lesson 14 - Next |
In Procore, the term retainge refers to the practice of withholding of a portion of a contract amount until the work is deemed satisfactorily complete. The withheld amount is specified in an agreement between the contracting party (the party paying for the work) and a contracted party (the person or company performing the work). Then, the withheld amount can be released as a progress payment. When work is substantially (or finally) complete, the withheld amount can be released as a final payment.
- Additional Information:
- To set the same percentage of retainage on all line items in the invoice, enter a value to apply to all line items in the invoice.
- To release retainage on all line items, enter a value to apply to all line items. This move the desired percentage from the 'Currently Retained' column to the 'Released This Period' column.
- Navigate to the project's Invoicing tool.
- Click the Subcontractor tab.
- Locate the commitment that you want to work with and click its link in the Commitment column.
- Click the Invoices tab.
- Locate the invoice to work with and click Edit.
- Click the Detail tab in the invoice.
- Click the Edit button.
- Choose one of the following:
Set Retainage on All Line Items
Release Retainage on All Line Items