Add and Manage Subtasks for a Lookahead Schedule

 Early Access
The following document describes functionality that is currently not available in all accounts. Please contact your Procore Account Manager for more information.

Objective 

To add and manage subtasks for lookahead schedules on the project's Schedule tool.

Background

A lookahead is a snapshot of the master schedule uploaded to Procore over a specified duration ranging from one to six weeks. The lookahead feature allows companies to manage schedule tasks on the master schedule in greater detail. You can use a lookahead to create subtasks, add notes to existing schedule tasks, and edit schedule tasks. In addition, schedule tasks and lookahead subtasks will carry over to each lookahead created if the dates overlap with one another.

Things to Consider  

  • Required User Permissions:
    • 'Admin' permissions on the project's Schedule tool.
  • Additional Information:
    • Edits and changes made on a lookahead will not reflect on the master schedule. 
  • Prerequisites:
    • To manage subtasks on a lookahead you must have already created a lookahead on the project's Schedule tool.

Manage Lookahead Tasks

Users can manage an individual task on a lookahead by its day-to-day progress and status. Tasks can be managed with the following options:

  • Critical: To mark a task as Critical on a lookahead, click the day and date box one time and a light red box will appear. 
    Notes: Click the day and date box for each day a task will be performed. 
                   A red box denotes a task is Critical.
  • Critical Complete: To mark a critical task as Complete, click the light red box a second time and the critical task turns dark red. 
  • Standard: To mark a task as Standard on a lookahead, click day and date once and a light blue box will appear.
    Notes: Click the day and date box for each day a task will be performed. 
                   A blue box denotes a task is Non-critical.
  • Standard Complete: To mark a standard task as complete, click the light blue box a second time and the standard task turns dark blue.
    Note: Critical and Standard tasks populate directly from the master schedule file that has been uploaded to project's Schedule tool. Users cannot designate a task as critical or noncritical and the colors of the boxes can't be modified. 

The following actions are also available:

Delete a Lookahead
  • Click the delete trash  icon to delete a lookahead.
    clipboard_e322c2efae240cf5868061c5370d700b5.png
    Note: Deleting a lookahead will not impact the master schedule or other lookaheads where dates overlap.
Create a Subtask
  1. Navigate to the project's Schedule tool. 
  2. Click the Lookaheads tab.
  3. Select the lookahead you want to add a Subtask to.
  4. Click the plus icon in the Notes column of schedule task  you want to add a subtask to and the Create Subtask menu will appear.
    Note: Click +Add Another Subtask to create another subtask.  
  5. Fill out the Create Subtask menu and click Create
  6. The Subtask will appear on the lookahead as .1 under the main task. 
    Note: You can add multiple Subtasks.
Edit a Task
  1. Navigate to the project's schedule tool. 
  2. Click the Lookaheads tab.
  3. Select the lookahead task you want to edit.
  4. In the Notes column of the task you want to edit, click the Edit Task  icon.
    edit-task-icon.png
  5. Fill out the Edit Task menu.
    edit-task-window.png 
  6. Click Update.
Delete a Task
  1. Navigate to the project's Schedule tool.
  2. Click the Lookaheads tab.
  3. Select the lookahead you want to delete a task from.
  4. In the Notes column of the task you want to delete, click the Task Info  icon.
    task-info.png
  5. Click the vertical ellipsis  on the Task menu and click Delete.
    delete-task-.png
  6. On the Delete Task window, click Proceed to delete the task from the lookahead. 
    delete-task-window.png