Create a Schedule of Values on a Prime Contract using the Project's Budget

Objective

To create line items on a prime contract's Schedule of Values (SOV) using the line items from a project's budget. 

Background

After your construction project's original budget is finalized in the project's Budget tool, it is recommended that you lock the budget. Once locked, you can use the steps below to quickly import your budget line items to your prime contract's SOV.

Example

When using this method, you have two (2) options:

  • Create one line item on the prime contract's SOV for each line item on the project's budget.
    The example below shows you the line items on a budget that can be used to create corresponding line items on a prime contract's SOV. For example, 01-000-Purpose: Labor, 01-002-Instructions: Labor, 01-010 Project Manager: Labor, and so on. 

    sov-individual-line-items.png
     
  • Create one line item on the prime contracts SOV for each division summary on the project's budget.
    The example below shows you all of the division summaries on a budget. For example, 01-General Requirements, 02-Site Construction, 03-Concrete, and so on. 

    sov-division-line-item.png

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Prime Contracts tool.
  • Limitations:

Prerequisites

Steps

  1. Navigate to the project's Prime Contracts tool. 
  2. Locate the prime contract that you want to update. Then click its Number link.
  3. Click the Schedule of Values tab.
  4. Scroll to the 'Create Schedule of Values from Budget' section. Then, choose one of the available options:

    prime-contract-create-sov-from-budget.png
     
    • Option Button 1
      This option creates one line item on the prime contract's SOV for each line item on the project's budget. 
    • Option Button 2
      This option creates one line item on the prime contract's SOV for the summaries of each division on the project's budget.
       In Beta
      If your company is participating in the Work Breakdown Structure (WBS) beta program, Option Button 2 is not supported. 
  5. ​Click Create.

 