Background
If you need to move materials to a new storage location, you can create a materials transfer. If the status of materials changes during the transfer, 'Quantity Available' inventory counts are updated accordingly.
Things to Consider
-
You can have multiple line items with different locations in a single transfer.
-
After you submit a transfer and the status is 'Final', you can only edit the following fields:
-
Attach files
-
Custom Fields
-
Notes
-
Post Transfer Condition
-
-
'Quantity Available' counts are updated when the transfer is submitted and the status is 'Final'.
-
Post-Transfer Item Condition
-
Quantities of 'Acceptable' materials are included in the 'Quantity Available' in your inventory.
-
Quantities of 'Damaged' and 'Unacceptable' Materials are excluded from the 'Quantity Available' in your inventory.
-
Prerequisites
-
Locations must already be created in Procore. See Add Locations to a Project.
Steps
-
Navigate to the project's Materials tool.
-
Click the Inventory tab.
-
Mark the checkbox next to the materials you want to transfer.
-
Click Add to New Document and select Transfer.
-
Select Transfer.
-
Enter the general transfer information.
-
Enter the transfer for each line item.
-
Save or submit the transfer.
-
Click Save as Draft to save the adjustment as a draft.
-
Click Submit to submit the adjustment as final.
-