Add Quantities to a Timesheet (Android)

Objective

To add quantities to a timesheet that can then be tracked in the Production Quantity Report.

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.
  • Installed production quantities refers to the actual amount installed on a project by a point in time.

Use the steps below to enter installed production quantities on a timesheet. One entered, they can then be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

Steps

Now that you have filled out your timesheet, perform the following actions before you submit:

  1. Tap Submit.
  2. Under 'Select an Option',  Submit and Add Quantities.

    submit-and-add-quantities.png
     Notes
  3. Tap Add Quantities.
  4. Tap Add Units.
  5. In the Units Installed Today field, enter the appropriate unit quantity.
  6. Optional: Enter any notes.
  7. Tap Apply to save your changes.