If you have already synced your budget and want to sync the updates made in Procore, complete these steps before exporting your updated budget to Integration by Ryvit:
After using the Project Financials + CMiC Connector to export a budget from Procore to CMiC, the import function to Procore will no longer be available for that job/budget.
The following functions are disabled in Procore until all synced data is visible in CMiC as the Budgeted Cost Amount.
The ability to unlock a Procore budget. See Unlock a Budget.
An accounting approver will accept the budget (see Accept or Reject a Budget for Export to CMiC). Once accepted, the system exports the budget data from Procore and syncs it to CMiC.
When the export is successful, go to the JC Original Estimates form in CMiC to review the exported Original Budget amounts. See your CMiC help system for instructions.
*After you sync the budget for the first time, you can also sync an updated Procore budget toCMiC.