Import a Prime Contract SOV from a CSV File

Objective

To update a prime contract's Schedule of Values (SOV) by uploading a Comma Separated Values (CSV) file to the Prime Contracts tool.

Background

A Schedule of Values (SOV) is a list of line items that details all of the agreed-upon costs (for example, labor, materials, and so on) on a project. Abbreviated as SOV, it itemizes the contract amount into individual pay items to show how the entire contract sum is allocated to all of the project's work. An SOV is also based on the project's approved budget and commonly used to determine progress payments to the contractor(s).

Things to Consider

Prerequisites

Steps

  1. Navigate to a project's Prime Contracts tool.
  2. Locate the prime contract to update. Then click its Number link.
  3. Click Schedule of Values.
  4. Optional: Under Import Schedule of Values from CSV, download one of the template options:

    prime-contract-import-sov-from-csv.png
    • Blank Template
      To download a blank template, click the Blank Template link.
      OR
    • One Showing Existing Line Items
      To download a template that includes any existing SOV line items, click the One Showing Existing Line Items link.
      This downloads a template named 'csv_import.csv' to the location on your computer specified in your web browser's settings. 
       Notes
      • Using your own template or modifying a file to match a template can result in an incompatible format which can lead to import failure and/or import errors.
      • After completing your SOV data entry in a template, continue with the import process.
      • While using a Procore template is marked (Optional), we recommend that you always download one of these templates to complete your SOV data entry. 
      • If the combination of the sub job, cost code, and cost type are non-budgeted for a line item, this line item will be added directly to the Budget with a "?" next to the line item. See Add a Partial Budget Line Item.
  5. Update the template with your SOV line items. 
     Notes
    • Do NOT add, rearrange, remove, or rename any of the columns or column headings in the template. 
    • To complete the import successfully, your data needs to be entered using the exact structure specified in the template.  
    • The cost code and cost type entries must exactly match the codes and types defined under Cost Codes in the project's Admin tool. See Add and Edit Project Cost Codes.

    Prime Contract example import csv.png
     
  6. Complete the data entry as follows:
    1. Cost Code Name
      The detailed name of the cost code number in the following format:
      'Division-Code - Title' (for example, 01-100 - Summary)
      Note: if you do not want to use a cost code, you must enter "None" in the Cost Code Name and Cost Code Number fields. 
    2. Cost Code Number
      The cost code number in the following format:
      'Division-Code' (for example, 01-100)
      Note: if you do not want to use a cost code, you must enter "None" in the Cost Code Name and Cost Code Number fields. 
    3. Description
      (Optional) A more detailed description of the line item.
    4. Line Item Type
      (Optional) The cost type associated with your cost code (for example Labor, Materials, and so on). See Default Cost Type List.
       Notes
      • You can modify the default cost types and add their own definitions to the list.
      • It is important that your data entries match your company's cost type list. For example, if the category type is Materials, use M and not m, materials, or Materials. Below are Procore's default Cost Types.
        • If you leave a cell in the Type column blank (as pictured above), Procore assigns the type as Other by default. 
        • If you input an invalid entry in a cell in the Type column, Procore also lists type as Other by default. 
      • The import process is case-sensitive. 
    5. Amount
      Enter a numeric value or the contract amount.
       Notes
      • The use of commas and/or the dollar symbol ($) is not required. For example, '15000' is the correct syntax.
      • If there is no dollar amount to enter, be sure to enter 0.00.
      • The import will not accept a blank cell. 
      • Blank lines still count as lines in the import process, so be sure to delete them from the end of the SOV file before importing.
  7. Specify the type of import/upload action to perform.
    • Delete existing line items, and add CSV as new items  
    • Keep existing line items, and add CSV as new items
  8. Select the modified CSV file.
  9. Click Import.
  10. Wait a few seconds, and then click the Schedule of Values tab and verify that the SOV was imported as expected.
  11. If you need to make further changes to the SOV, click Edit.
    • Manually add additional line items
    • Delete a line item
    • Change the selected cost code number
    • Edit a line item's description, type, and the contract amount
  12. Click Save.
    OR
    Click Save and Email if you want to save your changes, as well as forward a copy of the Prime Contract using Procore's built-in email feature. You'll also be able to specify recipients and include a brief message about the Prime Contract.

 