Close a Coordination Issue
Close a coordination issue once it is resolved and verified. Doing so clears the issue from your Navisworks® list in the Procore BIM Plugin, keeping your workspace organized. Don't worry about losing data—the web application permanently stores every coordination issue for your records.
Things to Consider
- Required User Permissions
- Additional Information:
- 'Standard' users cannot close coordination issues, but they can mark them as complete. Learn how to Mark a Coordination Issue as Complete.
- Closing an issue hides it in Navisworks®, but you can still view it in the project's Coordination Issues tool in the Procore web application.
Prerequisites
-
To close an issue from Navisworks® you must first Associate a Navisworks® Model with a Procore Project.
Steps
Choose the application you are working in and follow the steps on your computer.
To close an issue from Procore's Coordination Issues tool Show/Hide Details
- Navigate to the project's Coordination Issues tool.
- Find the issue you want to close by searching or filtering by assignee, status, or location.

- Click the issue to view its details in the side panel.

- Click Mark as Closed in the side panel.
To close an issue from Procore's Navisworks® with the Procore BIM Plugin Show/Hide Details
- Start Autodesk® Navisworks® on your computer.
- In the Procore tab, open the model.
- In the All Issues list, find the issue to close. To first review its details, click Info.
- Click Close.
To close an issue from Revit® with the Procore BIM Plugin Show/Hide Details
- Start Autodesk® Revit® and navigate to a 3D view in the Revit® project browser.
- Click the Procore tab.
- Click Coordination Issues.
- In the Coordination Issues panel, select the Procore project.
- On the coordination issue, click the information
icon. - Click Actions and select Mark as Closed.