Add Change Event Line Items
Objective
To add line items to a change event using the project's Change Events tool.
Background
There are three ways to add line items to a change event:
- Manually add each line item
This allows you to add line items one-by-one. - Add line items in bulk using the 'Add Line Items for All Commitments' link
This option creates a new line item on the change event for each line item on a commitment that is in the 'Approved' state. - Import Line Items from a CSV File.
Things to Consider
- Required User Permissions:
- 'Standard' level permissions or higher on the project's Change Events tool.
- 'Standard' level permissions or higher on the project's Change Events tool.
- Additional Information:
- For companies using Procore's Project Financials and Workforce Management tools, you can log changes to production quantities (for example, if the change event includes a production quantity change for additional drywall) on the Production Quantities tab. For details, see Record Changes to Production Quantities in a Change Event.
Prerequisites
Steps
Tip
Did you know a user with 'Admin' settings on the Change Events tool can turn the Change Events tool's 'Column Display' settings ON and OFF? For best results, your project's column display settings should be determined at the beginning of a project. To learn more, see How do the Change Events tool's column display settings work?- Navigate to the project's Change Events tool.
- Choose from these options:
- Click the Detail tab. Then find the change event to update and click Edit.
OR - Follow the steps in Create Change Events.
- Click the Detail tab. Then find the change event to update and click Edit.
- In the 'Edit Change Event' page, scroll to the 'Line Items' card.
- Choose from these options:
- To add one (1) new line item on the change event, click Add Line.
OR - To add line items in bulk using line items from all of the project's commitments in the 'Approved' status, click Add Lines for All Commitments.
OR - To import line items from a CSV file, see Import Change Event Line Items from a CSV File.
- To add one (1) new line item on the change event, click Add Line.
- Complete the line item data entry as follows:
- Budget Code
Select a budget code or click Create Budget Code. See What is a budget code in Procore's WBS?Tip
Need help creating a new budget code? For step-by-step instructions, see Create Budget Codes in Procore's Project Financials Tools. - Description
Enter a description for the line item. - Vendor
Select the vendor's company name from the drop-down menu. See Add a Company to the Project Directory. - Contract
Select the impacted purchase order or subcontract from the drop-down menu. See Create a Purchase Order or Create a Subcontract. - Qty
Enter a numeric value in this box to indicate the number of units that correspond to the unit of measurement that you specify. - UOM
Select a Unit of Measure (UOM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a Unit of Measure to the Unit of Measure Master List. - Unit Cost
Enter the monetary cost in this box to indicate the cost per unit of measurement. - Cost ROM
Enter a numeric estimation of the cost's Rough Order of Magnitude (ROM). This entry has NO financial impact on values in other Procore tools. You can add the ROM to the Budget by following the steps in Add Cost ROM, RFQ & Non-Commitment Cost Source Columns to a Budget View.NoteS
- If you are using the enhancements for unit-based financials, this column will capture unit changes to UOM on both Rev ROM and Cost ROM.
- If you follow those steps to show the ROM value in the budget, and the change event line item ends up having no cost, you will need to zero out the ROM to remove it from the budget
- Budget Code
- Click Update.
Next Step
See Also