Objective

To mark an existing task category as inactive so that it cannot be assigned to project level task items.

Things to Consider

Required User Permission: 'Admin' level permission on the company's Admin tool.

Steps

  1. Navigate to the company level Admin tool. 
    This reveals the Company Settings page.
  2. Under "Tool Settings," click Tasks.
  3. Mark the checkbox (2018-05-23_16-33-12.png) next to the category name you want to remove.
    Your changes are automatically saved.
    mark-category-inactive.png

See Also