Create Submittals

Background

In the construction industry, a submittal consists of information provided by subcontractors to the general contractor and design team for approval of equipment and materials before they are fabricated and delivered to a project. Submittals can include shop drawings, equipment cut sheets, or material samples. These allow architects and engineers to verify that the correct products will be installed in compliance with design and contract documents.

Using the Submittals tool helps project teams streamline the review process. Typically, a submittal manager—often a project manager or engineer—oversees the submittal throughout its lifecycle. While the person who creates the submittal is assigned as the manager by default, this role can be reassigned to ensure continuity if project team members change. Once the manager creates the submittal and the subcontractor provides documentation, it is sent to the design team for official review and approval.

Things to Consider

  • Required User Permissions

  • Additional Information:

    • Alternate methods for adding submittals to a project include:

    •  

      Configuration Settings: Show/Hide Fields

      At the start of a new project, a user with 'Admin' level permissions on the Submittals tool will typically configure the following settings for your project's Submittals tool:

      • Cost Code. The cost code for the submittal. Cost codes are managed in the 'Cost Code' segment in Procore's Work Breakdown Structure.

      • Default Submittal Manager. Select the desired submittal manager. See What is the 'Submittal Manager' role?

      • Distribution List. The people who will receive email notifications from Procore as the submittal progresses through the submittal workflow. If your project team has created any distribution lists in the Project Directory, you can select those lists here. See Add a Distribution Group to the Procore Directory.

      • Number & Revision. The submittal number and its revision number. See How are submittals numbered in Procore?

      • Submittal Schedule Calculations is a back end configuration option in Procore where the estimated response due dates are automatically calculated with a predefined lead time (for example, five (5) days). This calculation helps to facilitate timely responses from designated reviewers in the submittal's approval workflow.

      • Schedule Task: If the Schedule tool is active on the project, you can associate the submittal with task on the project schedule.

      • Specification. Denotes the corresponding section from the project's specifications book. 

      • Submittal Workflow Template. In Procore, a submittal workflow template provides users with 'Admin' level permission on the Submittals tool with the ability to define the submitter(s) and approver(s) for your project's submittal review process. You can create multiple workflow templates to suit the specific needs of your review process.

Steps

  1. Navigate to the project's Submittals tool.

  2. Click + Create and choose Submittal from the dropdown menu.

  3. Create a new submittal as follows:

​Add General Information

Complete the following General Information details as follows: Show/Hide Fields

 Note
Users with Standard permission to the Submittals tool are limited to viewing the following fields when creating a new Submittal: Title, Specification, Number & Revision, Submittal Type, Responsible Contractor, Received From, Final Due Date, Location, Linked Drawings, Distribution List, Ball in Court, Private, Description, Attachments
  • Specification. Denotes the corresponding section from the project's specifications book

  • Number & Revision. The submittal number and its revision number. See How are submittals numbered in Procore?

  • Submittal Package. The submittal package that contains the submittal. In Procore, adding submittals to a package is optional. The decision to add submittals to a submittal package is based on your project's requirements, which is determined by your company's or project's management team. For instructions, see Create a Submittal Package.

  • Status. The current status of the submittal. Only a user with 'Admin' level permission to the Submittals tool can change a submittal's status. See What are the default submittal statuses in Procore? and What is a 'Draft' Submittal?

    • Note: If a submittal is Open and has no workflow, the Ball in Court (BIC) is the Submittal Manager and the item should show in their My Open Items tool. If a submittal is Open and does have a workflow, the current workflow step assignee has the BIC. Once the workflow is complete, BIC returns to the Submittal Manager. If a submittal is Closed, the BIC is cleared.

  • Responsible Contractor. The company name of the contractor/subcontractor that is responsible for completing the work specified on the submittal.

  • Received From. The contact for the responsible contractor who provided the submittal information to the project team.

  • Submit By. Select the date by which a contractor/subcontractor must submit all relevant documentation (i.e., documents, drawings, manuals, plans, and so on) for the submittal to the project's design team for review.

  • Issue Date. The date the contractor/subcontractor submitted the submittal items (i.e., documents, plans, and so on) to your project team for the review process

  • Received Date. The date that the submittal information was received from the contractor/subcontractor responsible for the performing work associated with the submittal.

  • Final Due Date. The due date by which all approvers on the submittal workflow must submit a response.

    • Note: When the Final Due Date, occurs, the system sends an automated email notification to notify users that the submittal is overdue. If your system is configured to use sequential approval, the notification goes to the Submittal Manager and the BIC person on the approval workflow. If your system is configured to use parallel approval, the notification goes to the Submittal Manager and members of the approval workflow.

  • Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.

  • Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.

  • Cost Code. The cost code for the submittal. Cost codes are managed in the 'Cost Code' segment in Procore's Work Breakdown Structure.

  • Submittal Manager. The name of the submittal manager. This is the person who is responsible for overseeing the submittal throughout its lifecycle in Procore. Each submittal can have a different submittal manager or your project team can configure a 'Default Submittal Manager' for all of your submittals. See What is the 'Submittal Manager' role?

  • Type. The information type associated with the submittal. The default type selections in Procore include: Document, Pay Request, Payroll, Plans, Prints, Product Information, Product Manual, Sample, Shop Drawing, Specification, and Other. See Create Custom Submittal Types.

  • Private. Indicates privacy settings for the submittal. When a submittal is marked 'Private', it is only visible to users with 'Admin' level permissions on the Submittals tool, users in the Submittal Workflow, and members of the submittal's Distribution List. Users with the 'View Private Submittals Associated to Users within Same Company' granular permission enabled on their permissions template can also view a submittal marked 'Private' if another user in their company is associated with the submittal. See Mark a Submittal as Private.

  • Description. Informative details, notes, and/or actions that describe the submittal.

  • Attachments. Attach any relevant files. You have these options:

    • Click Attach File(s) and then choose the appropriate option from the shortcut menu that appears.

    • OR Use a drag-and-drop operation to move files from your computer into the grey Drag and Drop File(s) box.

  • Distribution List. The people who will receive email notifications from Procore as the submittal progresses through the submittal workflow. If your project team has created any distribution lists in the Project Directory, you can select those lists here. See Add a Distribution Group to the Procore Directory.

Submittal Schedule Information (If Enabled)

If enabled, complete the Submittal Schedule Information details: Show/Hide Fields

Submittal Schedule Calculations is an optional feature that you can enable. See Enable Submittal Schedule Calculations.

  • Schedule Task: If the Schedule tool is active on the project, you can associate the submittal with task on the project schedule.

  • Design Team Review Time. The number of days allotted for the design team's review on the submittal.

  • Lead Time. Lead Time refers to the amount of time it takes to complete a process from start to finish. In construction, it can refer to the amount of time between order placement and delivery of the order on a job site. It can also refer to the amount of time a client must wait between project initiation and the contractor's start date.

  • Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.

  • Internal Review Time. The number of calendar days that your project's design team requires to ensure the submittal is properly reviewed.

Update the Delivery Information

  • Anticipated Delivery Date: View the date displaying in the Anticipated Delivery Date. This is the date between the 'Lead Time' and when the submittal was distributed, and it will not populate upon the creation of the submittal. This date is calculated by Procore once the submittal has been distributed. See Distribute a Submittal.​​

  • Schedule Task: If you have enabled the Schedule tool on the project and integrated an Asta Powerproject, Microsoft Project, or Oracle Primavera schedule with Procore, you are permitted to select a project task from the Schedule Task drop-down list when you have a user account that has been granted 'Read-Only' level permission or higher on the Schedule tool. This is for reference only.

  • Confirmed Delivery Date: Select the date the subcontractor or supplier confirmed the freight would arrive using the Confirmed Delivery Date calendar.

  • Actual Delivery Date: Select the date the material arrived on site using the Actual Delivery Date calendar. Typically, this value is updated by the project superintendent.

Apply a Submittal Workflow Template

A user with 'Admin' level permission to your project's Submittals tool can create one (1) or more submittal workflow templates which you can then to a new submittal when you first create it. This saves data-entry time by preventing you from having to add a new submittal workflow each time you create a submittal.

  1. Under Submittal Workflow, do the following:Submittal Workflow Add Template

    1. Select a Template. Select a workflow template from the drop-down list.

    2. Notes:

      • This drop-down list is only visible and available to users with 'Admin' level permission on the Submittals tool.

      • This action applies the person(s) named on the submittal workflow template to your submittal.

      • To learn how submittal workflow templates are created, see Manage Submittal Workflow Templates.

  2. Continue by modifying the Name, Role, and Days to Submit/Response fields as needed for the submittal. Your changes only affect the workflow on the submittal, your changes do NOT affect the submittal workflow template.

  3. (Optional) Continue with the steps in Add Users to the Submittal Workflow.

Add Users to the Submittal Workflow

  1. Under Submittal Workflow, do the following for each desired line item in the submittal:

    • Name. Start typing a project user's name in the Search box. Then select the appropriate user from the list.

      • If you want to require a response from the user, place a mark in the checkbox next to their name.

      • If you do NOT want to require a response from the user, remove the mark from the checkbox.

        • Note: If you are adding more than one user to a parallel approval workflow group, the Ball In Court Responsibility will shift to the next workflow group after all of the people marked required in the group submit a response to the submittal.

    • Role. Select Approver or Submitter from the list. See What is the difference between a submitter and approver in submittals?

      • Notes:

        • To be designated as an approver, the person must exist in the Project level Directory tool (see Add a User Account to the Project Directory) and must also be granted 'Admin' or 'Standard' level permissions to the Submittals tool (see Set User Permissions for the Submittals Tool).

        • If you are a user with 'Standard' level permissions to the Submittals tool, you can only add users with 'Admin' level permissions to the workflow.

        • If you plan to add a Submitter to the submittal, we recommend that you designate a Submittal Manager as the first approver in the submittal's sequential approval workflow. This gives the Submittal Manager an opportunity to ensure the submittal is thoroughly reviewed by your internal stakeholder before it is sent to the users in the next step on the submittal workflow.

        • If you are a user with 'Admin' level permissions to the Submittals tool, you can add users with either 'Admin' or 'Standard' level permissions to the workflow.

          • Note: If you want the submittal workflow to use sequential approval, add only one user to each line item in the workflow. If you want a step in the submittal workflow to use parallel approval, add two or more users to a line item.

    • Due Date. Select a date from the calendar for the submittal response to be due.
      Note: The 'Due Date' field is automatically populated based on the default number of days specified on the Submittals tool's Configure Settings page. See Configure Settings: Submittals Tool. The due date also respects which days are set as 'working days' for the project. See Set Project Working Days.

  2. Click Add Step.

  3. Repeat these steps to add another user to the workflow.

  4. If you want to change the order of the workflow steps, do the following:

    1. Grab the line item by the vertical grip (⋮⋮).

    2. Use a drag-and-drop operation to move the line item into the desired order.

      Submittals Change Order Table

Update and Send the Submittal for Review

When finished with the steps above, do one of the following:

  • To save your changes without sending an email to members of the submittal workflow, distribution list members, and submittal manager, click Create.

  • To save your changes and to send an email notification to alert the members of the submittal workflow and to alert the members of the distribution list, click Create & Send Emails.