Edit a Commitment's Schedule of Values (iOS)
Objective
To edit the schedule of values on a commitment using the Procore app on an iOS mobile device.
Things to Consider
- Required User Permissions:
    
- 'Admin' level permissions on the project's Commitments tool.
 
 - Additional Information:
    
- This action can be performed in offline mode if the asset/item was previously viewed and cached on your mobile device. Tasks performed in offline mode will sync with Procore once a network connection is reestablished.
 
 
Prerequisites
- Create a Purchase Order or Create a Subcontract
 - Set the accounting method on the contract. See Edit the Advanced Settings Tab on a Commitment.
 
Steps
- Navigate to the project's Commitments tool using the Procore app on an iOS mobile device.
 - Tap the commitment you want to edit the schedule of values for.
 - Tap Schedule of Values.
 - Tap the item you want to edit.
 - Tap Edit.
 - Tap into a field to modify the appropriate information.
 - Tap Save.
 