What source columns are available in Procore's budget or forecasting views?
Background
In a Procore budget or forecasting view, a source column pulls source data from corresponding columns in the Financial Management tools. Some Source Columns also have Advanced Options. To configure source columns for a budget or forecasting view, see Create a Budget View or Create a Forecasting View.
Example
This image shows the Source Column configuration options in the 'Column Details' panel when configuring a column. When options are available, users can select data sources from drop-down lists, mark checkboxes to select options, and set applicable filter criteria from drop-down lists.
Answer
When configuring a new or existing Source Column in a budget or forecasting view, you can mark one or more checkboxes to turn the corresponding data columns ON. Remove the checkmarks to turn columns OFF. Users can also configure group and filter options for source columns when available.
|
Column Source |
Source Tool |
Data Column |
Group or Filter Options |
|---|---|---|---|
|
Budget Change Production Qty |
Budget |
Budget Change Production Quantities |
|
|
Budget Change Unit Quantity |
Budget |
Budget Change Unit Quantity |
Status |
|
Budget Changes |
Budget |
Budget Change Adjustments |
|
|
Budgeted Production Quantity |
Budget |
Budgeted Production Quantity |
N/A |
|
Change Event Production Qty |
Change Events |
ROM (Rough Order of Magnitude) |
|
|
Change Event Unit Qty |
Change Events + Change Orders |
Revenue ROM (Rough Order of Magnitude) |
|
|
Change Event Unit Qty |
Change Events + Change Orders |
ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change Events + Change Orders (2- or 3- tier required) |
Revenue ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change Events + Change Orders (2- or 3- tier required) |
ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change Events |
Budget ROM (Rough Order of Magnitude) |
Budget Changes |
|
Change Events |
Change Events + Change Orders (2- or 3- tier required) |
RFQ (Request for Quote) |
|
|
Change Events |
Change Events |
Change Event Latest Cost |
|
|
Change Events |
Change Events |
Change Event Latest Price |
|
|
Commitment |
Commitments |
Subcontracts |
Status |
|
Commitment |
Commitments |
Purchase Order Contracts |
Status |
|
Commitment |
Commitments |
Change Orders (CCOs) |
|
|
Direct Costs |
Direct Costs |
Direct Costs |
|
|
Direct Costs Unit Qty |
Direct Costs |
Direct Costs Unit Quantity |
|
|
Equipment Timecard Hours |
Equipment |
Equipment Timecard Hours |
N/A |
|
ERP Job Costs |
ERP Integrations |
|
N/A |
|
Installed Production Quantity |
Budget |
Installed Production Quantity |
N/A |
|
Owner Invoices |
Prime Contracts |
Owner Invoices |
|
|
Prime Contracts |
Prime Contracts |
Prime Contracts |
Status |
|
Prime Contracts |
Prime Contracts + Change Orders |
Change Orders (PCCOs) Advanced Options: |
|
|
Prime Production Qty |
Prime Contracts + Change Orders |
Change Orders Production Quantity Advanced Options: Change Order Requests Production Quantity and Potential Change Orders Production Quantity can be filtered by Status or Scope. |
|
|
Prime Unit Qty |
Prime Contracts + Change Orders |
Change Orders (PCCOs) Unit Quantity Advanced Options: |
|
|
Production Quantities |
Budget |
Budgeted Production Qty |
N/A |
|
Production Quantities |
Budget |
Budget Change Production Quantities |
|
|
Production Quantities |
Prime Contracts + Change Orders |
Prime Contract Change Orders Production Quantity |
|
|
Production Quantities |
Change Events |
Change Events Production Quantity ROM |
|
|
Production UOM |
Budget |
Budgeted Production UOM |
N/A |
|
Subcontractor Invoices |
Commitments |
Subcontractor Invoices |
|
|
Timecard Entry Hours |
Timecard |
Timecard Entry Hours |
Status |