Skip to main content
Procore

Does the master schedule update when I make a change to a Lookahead schedule?

Answer

No. Although a lookahead schedule reads from the schedule tasks on the master schedule, nothing done in lookaheads edits the master schedule. Users have the ability to add, remove, and create subtasks on a lookahead schedule, but these changes will not be reflected on the master schedule.