There are two (2) ways to link an existing change order or a commitment to a change event line item:

Link a Commitment's SOV Line Item to a Change Event Line Item

  1. Navigate to the project's Commitments tool.
  2. Locate the commitment that you want to link and click Edit
  3. Click Schedule of Values.
  4. Click Edit.
    Note:
    Procore will restrict you from editing the commitment when the following is true:
    • There are one or more change orders in the Approved status. 
    • One or more invoices have been created for the commitment. 
  5. Under Add Line Item, select the appropriate line item from the Change Event Line Item drop-down list. 
  6. Enter the following information:
    • Cost Code. The cost code from the change event will populate. 
    • Description. Enter a description for the line item. 
    • Type. The type from the change event will populate. 
    • Amount. Enter the amount for the line item. 
  7. Click Save

Link a Change Order's SOV Line Item to a Change Event Line Item

  1. Navigate to the Commitment tool. 
  2. Click Change Orders.
  3. Click Edit next to the Change Order with the line item you want to link to a change event.
  4. Click Schedule of Values.
  5. Click Edit.
    Note: Procore will restrict you from editing the change order if there one or more change orders in the Approved status. 
  6. Under Add Line Item, select the appropriate line item from the Change Event Line Item drop-down list. 
  7. Enter the following information: 
    • Cost Code. The cost code from the change event will populate.
    • Description. Enter a description for the line item. 
    • Type. The type from the change event will populate. 
    • Amount. Enter the amount for the line item. 
  8. Click Save