Import a Project Schedule
Background
Importing your schedule centralizes your project's timeline, allowing the entire team to access the most current data in one place.
Things to Consider
-
Required User Permissions: 'Standard' level permissions or higher on the project's Scheduling tool.
-
Supported File Types: Procore supports .ppx (Phoenix), .mpp (Microsoft Project), and .xer (Primavera P6).
-
Note: When importing, the project calendar is carried over directly from the native source file.
Important
At this time, the latest cloud versions of P6 .xer files are not supported.
Steps
-
Navigate to the project's Scheduling tool.
-
Click Import.
-
Click Attach File(s) and select your schedule file, or drag-and-drop the file into the upload area.
-
Click Import.
See Also
- Configure Your Project's Scheduling Path
- Reset a Project Schedule