Manage Activity Dependencies
Background
Dependencies define the sequence of work by linking predecessor and successor tasks. Procore supports four dependency types: Finish-to-Start (FS), Start-to-Finish (SF), Start-to-Start (SS), and Finish-to-Finish (FF). Managing these links ensures that your schedule accurately reflects project workflows and that the critical path is calculated correctly.
Things to Consider
-
Required User Permissions: 'Standard' level permissions or higher on the project's Scheduling tool.
-
Note: In an editable schedule (Option 2), Procore dynamically updates the logic chain in real time as dependencies are changed.
Steps
Create a Dependency
You can link tasks using three different methods:
-
Drawing on the Gantt Chart: Click the circle at the end of a predecessor taskbar and drag the connection line to the beginning of the successor taskbar.
-
Connect and Sequence (Bulk):
-
Mark the checkboxes for the tasks in the table in the order they should occur.
-
Right-click any of the selected tasks and select Connect and Sequence.
-
-
Manual Entry: Click into the Predecessors column for a task and type the row number of its predecessor.
Adjust Lag Time
-
Locate the dependency arrow connecting two tasks on the Gantt chart.
-
Double-click the dependency arrow.
-
Enter the number of days in the Lag field.
-
Click Save.
Remove a Dependency
-
Double-click the dependency arrow on the Gantt chart that you want to remove.
-
Review the predecessor and successor information to confirm it is the correct link.
-
Click Delete.
See Also
- Manage Schedule Activity and Hierarchy
- Add Activities to a Schedule
- Set Date Constraints