Objective

To view see the Activity Feed of Lookahead schedules on the project's Schedule tool.

Things to Consider

  • Required User Permissions:
    • Read-only and above permissions on the project's Schedule tool with the 'View the Change History of a Lookahead' granular permission.

Steps

  1. Navigate to the project's Schedule tool.
  2. Click the Lookaheads tab.
  3. Click Activity Feed to show the change history of the entire Lookahead.  

 

If you would like to learn more about Procore's scheduling software and how it can help your business, please visit our construction scheduling software product page icon-external-link.png.