Void Materials Requirements
Things to Consider
-
You can only void a 'Final' requirements document. If a document is 'Closed', it must be reopened.
-
Quantities are removed from 'Required' Inventory.
Prepare Materials for Import
-
Void a Line Item
-
Void a Requirements Document
Void a Line Item
-
Navigate to the project's Materials tool.
-
Click the Requirements tab.
-
Click the requirements document name.
-
In the 'Items' section, click the void
icon next to the line item. -
Optional: Enter notes.
-
Click Void Line to confirm.
Void Requirements
-
Navigate to the project's Materials tool.
-
Click the Requirements tab.
-
Click the requirements document name.
-
Click the vertical ellipsis
for the receipt and select Void Requirement.

-
Optional: Enter notes.
-
Click Void Requirement to confirm.