Void an Inter Project Transfer
Things to Consider
-
Inter Project Transfer documents must be in a 'Final' state.
-
If each line item is voided, the Inter Project Transfer document also becomes void.
-
Voiding line item voids the corresponding line item in the Shipment.
-
Voiding the entire Inter Project Transfer voids the corresponding Shipment.
-
Impacts after Voiding
-
Quantities are moved back to the 'From Location' in their 'Pre-Transfer Condition'.
-
Steps
-
Void a Line Item
-
Void a Transfer
Void a Line Item
-
Navigate to the project's Materials tool.
-
Click More and select Inter Project Transfers.
-
Click the inter project transfer number.
-
In the 'Items' section, click the void
icon next to the line item. -
Optional: Enter notes.
-
Click Void Line to confirm.
Void an Inter Project Transfer Document
-
Navigate to the project's Materials tool.
-
Click More and select Inter Project Transfers.
-
Click the inter project transfer number.
-
Click the vertical ellipsis
for the document and select Void Inter Project Transfer.

-
Optional: Enter notes.
-
Click Void Inter Project Transfer to confirm.