Void an Inter Project Transfer

Things to Consider

  • Required User Permissions

  • Inter Project Transfer documents must be in a 'Final' state.

  • If each line item is voided, the Inter Project Transfer document also becomes void.

  • Voiding line item voids the corresponding line item in the Shipment.

  • Voiding the entire Inter Project Transfer voids the corresponding Shipment.

  • Impacts after Voiding

    • Quantities are moved back to the 'From Location' in their 'Pre-Transfer Condition'.

Steps

  • Void a Line Item

  • Void a Transfer

Void a Line Item

  1. Navigate to the project's Materials tool.

  2. Click More and select Inter Project Transfers.

  3. Click the inter project transfer number.

  4. In the 'Items' section, click the void icon - ban icon next to the line item.

  5. Optional: Enter notes.

  6. Click Void Line to confirm.

Void an Inter Project Transfer Document

  1. Navigate to the project's Materials tool.

  2. Click More and select Inter Project Transfers.

  3. Click the inter project transfer number.

  4. Click the vertical ellipsis Icon Vertical Ellipsis for the document and select Void Inter Project Transfer.
    materials - document - ellipsis

  5. Optional: Enter notes.

  6. Click Void Inter Project Transfer to confirm.