Things to Consider
-
Adjustment documents must be in a 'Final' state.
-
If each line item is voided, the Adjustment document also becomes void.
-
Impacts after Voiding
-
If quantities had been added in the adjustment, they are removed from stock and the location where they were added.
-
If quantities had been removed in the adjustment, they are added to stock in their previous location in 'Acceptable' condition.
-
Steps
-
Void a Line Item
-
Void an Adjustment
Void a Line Item
-
Navigate to the project's Materials tool.
-
Click More and select Adjustments.
-
Click the adjustment number.
-
In the 'Items' section, click the void
icon next to the line item. -
Optional: Enter notes.
-
Click Void Line to confirm.
Void an Adjustment Document
-
Navigate to the project's Materials tool.
-
Click More and select Adjustments.
-
Click the adjustment number.
-
Click the vertical ellipsis
for the document and select Void Adjustment.

-
Optional: Enter notes.
-
Click Void Adjustment to confirm.