Finalize a Materials Adjustment
Things to Consider
-
An adjustment must be submitted before it can be reviewed and finalized.
-
When an adjustment is finalized, the status is changed to 'Final'.
-
After an adjustment has been finalized, you cannot change the status or edit core details. However, you can still add notes, attach files, or update custom fields.
-
Finalizing an adjustment updates each item’s 'Quantity Available' inventory count.
Steps
-
Navigate to the project's Materials tool.
-
Click the Adjustments tab.
-
Click the adjustment number.
-
Click Finish Review.
-
Select Move back to Draft if there changes that need to be made to the receipt.
-
Select Mark as Final to finalize the receipt.
-