Things to Consider
-
Required User Permissions:
-
'Standard' or 'Admin' level permission to the project's Document Management tool.
Note: You must be part of a permission group with the 'View Change History' document permission enabled.
-
Steps
-
Navigate to the project's Document Management tool.
-
Open the document that you want to view.
-
On the right side of the viewer, click the info
icon.
Note: The workflowpanel may open automatically if a workflow is applied to the item. Click the x to close the panel and select the info
icon instead. -
Scroll down to the bottom of the Information panel.
-
Click Change History.
This opens a panel that lists the changes that have been made to the document in the project. The following information is shown:-
Date: The date and time the change was made.
-
Action By: The name of the user who made the change.
-
Changed: A description of the change.
-
From: The state or attribute that the document changed from.
-
To: The state or attribute that the document changed to.
Note
The Change History now tracks the following placeholder actions:
- Placeholder created: Records when the placeholder was initially added.
- File uploaded into Placeholder: Records when a file was first attached to the placeholder.
- Status: Tracks transitions between states, for example, from 'Awaiting File' to 'Approved'.
- Placeholder submitted: Records when the document is officially submitted to the project.
-