Objective

To create Quantity entries in the project's Daily Log tool.

Background

The Quantities section lets you input tracking information about the amount of materials that are used on a given day.

Things to Consider

  • Required User Permissions: 'Standard' or 'Admin' on the project's Daily Log tool.

Steps

  1. Navigate to the project's Daily Log tool.
  2. Scroll to the Quantity section.
  3. Enter the following information:
    • #: This uneditable field counts the number of entries in a section (e.g. the first entry created will be # 1, and the second entry will be # 2).

    • Log Date: This field specifies the date that the daily log entry applies to. This field will only display when viewing multiple days in the Daily Log tool and is uneditable.

    • Cost Code: Select from the drop-down menu the cost code associated with the entry. 

    • Quantity: Enter the total number of the specified materials placed on the site that day.

    • Units: Enter the types of units that were delivered.

    • LocationSelect or enter a location from the Location drop-down menu.
      Note: You have the option to select an existing location from the list, or you can add a multi-tiered location to an item.

    • Comments: Enter any comments that may help clarify the entry.

  4. Click Create.

 