Create Resource Assignments
Background
Assignments allow you to manage your resources by assigning resources to projects. Assignments can also be used for forecasting and planning future work. You can keep these assignments private until you are ready to notify the assignee or other members of your team.
You can bulk create assignments with the new Assignments Gantt. You can also make assignments to fill resource requests. See Fill a Resource Request.
Things to Consider
-
You can manage user visibility of assignments with assignment request statuses. See Configure Assignment Request Statuses for Resource Planning.
-
Linked users
that are given resource assignments are automatically added to the project. -
When equipment is assigned a Resource Assignment from the Assignment Gantt (Beta), it is automatically added to the project.
-
Timesheets
-
If creating a Timesheet for a user with an assignment, their start and stop times are automatically filled in to the timesheet based on their assignment in Resource Planning.
-
Data syncing between Resource Planning and Procore is required. See What is Data Syncing for Resource Planning?
-
Assignees must be 'Users' in Procore, and not 'Contacts'. See What people information is synced between Resource Planning and the Procore Company Directory?
-
Steps
You can create resource assignments from the following places:
Tip
You can bulk create assignments using the Assignment Gantt (Beta).
Create a Resource Assignment from the Assignments Boards
On the Assignments Boards, you can create a resource assignment the in following ways:
-
The 'New' Button
-
Drag and Drop from the Resource Bench
Create a Resource Assignment with the 'New' Button
-
Navigate to the Company level Resource Planning tool.
-
Click Assignments and select Assignments Boards.
-
Click New.
-
-
Click Save to save the assignment.
OR
Click the caret
icon and select Save and Alert to save the assignment and send an Assignment Alert to the assignee.
Create a Resource Assignment using Drag and Drop
-
Navigate to the Company level Resource Planning tool.
-
Click Assignments and select Assignments Boards.
-
Locate your 'Resource Bench'. See What is the 'resource bench' in Resource Planning?
-
Locate the person you want to assign. See Search, Sort, and Filter People on the Assignments Boards.
-
From the 'Resource Bench', use a drag-and-drop operation to move the assignee's name to the project. See What is the 'resource bench' in Resource Planning?
-
-
Click Save to save the assignment.
OR
Click the caret
icon and select Save and Alert to save the assignment and send an Assignment Alert to the assignee.
Create a Resource Assignment from the Assignments Gantt
-
Navigate to the Company level Resource Planning tool.
-
Click Assignments and select Gantt.
-
Click New.
-
-
Click Save to save the assignment.
OR
Click the caret
icon and select Save and Alert to save the assignment and send an Assignment Alert to the assignee.
Create Resource Assignments from the Assignments Gantt (Beta)
Note: Users given assignments this way are also added to the project in the company's Directory.
In Beta
This feature is in beta and available for customers using the Resource Planning tool.
Tip
You can also create this by creating a copy of an existing item on the Assignments Gantt.
-
Navigate to the Company level Resource Planning tool.
-
Click Assignments and select Gantt (Beta).
-
On the list, right click the project, category or subcategory for the assignment and select New Assignment.
Note: You can also hover over the project, category, or subcategory and click the vertical ellipsis
and select New Request. -
-
-
Fill out the Additional Information. See Configure Custom Fields for Resource Planning.
-
Optional: Enter Scope of Work to describe the scope of work.
-
Optional: Enter Assignment Instructions to provide additional instructions.
-
Optional: Enter Comments.
-
Click Create.
Tip
Click the undo
icon to undo an action. Click the redo
icon redo a previously undone action.
Create a Resource Assignment from the Assignments List
-
Navigate to the Company level Resource Planning tool.
-
Click Assignments and select Assignments List.
-
Click Create.
-
-
-
Fill out the Additional Information.
-
Optional: Enter Scope of Work to describe the scope of work.
-
Optional: Enter Assignment Instructions to provide additional instructions.
-
Optional: Enter Comments.
-
Click Create.
Send Assignment Alert Updates
After you create or update an assignment, send an alert to the assignee.