Set Planned Amounts & Budget Line Items
Background
Setting planned amounts as lump sums, as high-level budget items, or simply syncing them with the Project level Budget tool allows capital planners to establish project budget constraints and plan projected costs into a multi-year capital plan.
Things to Consider
-
Required User Permissions:
-
'Standard' or 'Admin' level access to Capital Planning.
-
-
Additional Information
-
Program or project structures must be configured in Capital Planning.
-
Steps
Set Planned Amount as a Lump Sum
-
Navigate to the Capital Planning tool.
-
Click the name of the program or project you want to update.
-
Click Edit.
-
In the Planned Amount field, select Lump Sum as the type.
-
Enter the total dollar amount.
-
Click Save.
Set Planned Amount as Line Items
-
Navigate to the Capital Planning tool.
-
Click the name of the program or project you want to update.
-
Click Edit.
-
In the Planned Amount field or grid, select Line Items.
-
Add or update individual cost code allocations.
-
Click Save.
Sync Planned Amounts with Budgets
-
Navigate to the Capital Planning tab.
-
To sync the Planned Amount for an active project:
-
Select Project Budget in the Planned Amount Type column.
-
Confirm the amount matches the current budget in the project-level Budget tool.
-
For Active Projects:
-
Select the option to sync with the Project Budget (Original or Revised Budget).
Note: Changes to the budget in the Procore® Budget tool will automatically update the Planned Amount in Capital Planning.
-
-
For Concept Projects:
-
The Planned Amount is pre-populated with the amount from the Estimated Budget.
-
-
-
To include or exclude a project from the total plan calculations:
-
Locate the In Plan toggle for the project.
-
Click the toggle to the On or Off position.
-
Confirm the Grand Total footer updates to reflect the change.
-