Capital Planning Table
Background
The Capital Planning table provides a centralized view of both active and concept projects, organized in a hierarchy of programs. This tool allows you to manage high-level budgets, track project stages, and forecast spending across your entire portfolio.
Things to Consider
-
Required User Permissions:
-
'Standard' or 'Admin' level permissions on the Company level Capital Planning tool.
-
-
Additional Information:
-
The table displays projects in all stages from Concept through Course of Construction. Closed, archived, and inactive projects do not appear.
-
To view or edit data, ensure you have the appropriate Standard or Admin level permissions on the Company level Home page.
-
The Remaining to Spread column is automatically calculated using the following formula:
$ Planned Amount - $Job to Date Costs - $Sum of Future Monthly Forecasts. -
All budget values are displayed in Arabic numerals. Negative values are indicated by parentheses. For example, $10,000.00.
-
Prerequisites
Navigate to the Capital Planning company-level menu item located under Financial Management in the Procore menu.
Steps
Set a Planned Amount
-
Locate the project row you want to modify.
-
Click the Planned Amount cell.
-
Enter the budget value.
-
Active Projects: If no amount is set, Procore defaults to the Revised Budget from the project's Budget tool.
-
Concept Projects: If no amount is set, Procore defaults to the Estimated Budget from the Project Admin tool.
-
Programs: Each program rolls up the project budgets beneath it, and higher-tier programs roll up the budgets of every program below them.
-
Create Detailed Budget Line Items
-
Click the Planned Amount for a specific project.
-
Select High Level Budget Items.
-
Add line items. For example, Hard Costs, Soft Costs.
-
Choose one of the following methods to enter values:
-
Enter a lump sum amount.
OR -
Enter a quantity and unit cost to perform a unit-and-quantity calculation (quantity x unit cost).
-
Enter a %markup to perform a % calculation to add tax or contingency.
-
-
Click Save to update the total Planned Amount.
View Budget Data for Active Projects
-
Review the read-only columns pulled from the Procore Standard Budget View:
-
Original Budget
-
Revised Budget
-
Job to Date Costs
-
Estimated Cost at Completion
-
Forecast to Complete
-
-
Optional: To view how a column is calculated, hover over the column header to see a tooltip.
-
Optional: Click the Budget icon to open the project's Budget tool in a new window.
Enter Forecasts
-
Scroll to the desired year, quarter or month Forecast column.
-
Click into the cell for the specific year, quarter, or month and project you want to forecast.
-
Enter the forecasted spend amount.
-
The Remaining to spread column will update to show unallocated funds and automatically subtracts job-to-date costs and future monthly forecasts from the planned amount.
For example: <$ Planned Amount> - <$Job to Date Costs> - <$Sum of future Monthly Forecasts>. -
Program rows and the Grand Total row will roll up these forecasts automatically.
-
Yearly and quarterly forecasts are spread linearly across the month forecasts corresponding to each year or quarter.
-