Re-import an Original Estimate from the Viewpoint® Vista™ Integration by Ryvit

Objective

To re-import an original estimate from the Viewpoint® Vista™ Integration by Ryvit into the project's Budget tool.

Background

If your company has previously imported a budget from Viewpoint® Vista™ Integration by Ryvit into a Procore project, users will typically make budget modifications in Procore. Should someone make changes to the original estimate in Viewpoint® Vista™ Integration by Ryvit, it must be re-imported into Procore so that the data is synchronized between the two systems. To do this, use the steps below. 

Things to Consider

  • Required User Permission:
    • 'Standard' level permission or higher on the ERP Integrations tool.
  • Prerequisites:
    • The original estimate must be established in Viewpoint® Vista™ Integration by Ryvit prior to the import.
    • The Budget tool must be enabled as an active tab on the project.
    • The Viewpoint® Vista™ Integration by Ryvit job must be added and synced with the Procore project. See Add a Viewpoint® Vista™ Integration by Ryvit Job to Procore.
    • The project's budget must be unlocked. See Unlock a Budget.
  • Additional Information:
    • If a Cost Code/Cost Type combination exists on the job in Viewpoint® Vista™ Integration by Ryvit, its cost estimate must be greater than zero (>$0) in order to create a budget line item in Procore.
    • Any updates on the original estimate that have been entered in Viewpoint® Vista™ Integration by Ryvit will be moved to Procore during the import (or re-import) process.

Steps

  1. Navigate to the ERP Integrations tool.
    The Viewpoint® Vista™ Integration by Ryvit page appears. 
  2. Click the Budgets tab.

    vv-click-budget-tab.png
     
  3. Under Filter Estimates By, click Synced.

    vv-budget-synced.png

    This reveals a list of successfully imported cost estimates from Viewpoint® Vista™ Integration by Ryvit. 
  4. Locate the desired cost estimate.
    Notes:
    • Each line item shows the Project Name and Total Estimate.
    • The Total Estimate includes the Current Viewpoint® Vista™ Integration by Ryvit Total, Current Procore Total, and New Procore Total On Re-Import.
  5. Click Re-import.
    Note: If the Re-import button is grayed out and unavailable, the budget must be unlocked before it can be re-imported. See Unlock a Budget

    vv-re-import.png
     
  6. In the 'Please Confirm' box that appears, click OK to confirm the re-import action.

    vv-please-confirm-reimport.png

    The system will override the existing value on the existing Procore budget with the value from Viewpoint® Vista™ Integration by Ryvit. The 'Successfully reimported to Procore' message appears when the process is complete.
  7. If you want to confirm that the Viewpoint® Vista™ Integration by Ryvit estimate was imported, click the hyperlink for the desired line item in the Project Name column.
    This opens the project's Budget tool. See Budget

See Also

The Viewpoint® Vista™ Integration by Ryvit is the product of a partnership between Procore and Ryvit, a third-party developer. Viewpoint, Inc. is not affiliated with this connector. All Viewpoint® Vista™ marks and logos are owned by Viewpoint, Inc.