Skip to main content
Procore

Which fields in the RFIs tool can be configured as required, optional, or hidden?

Background

In the table below:

  • A GREEN checkmark (icon-green-checkmark.png) indicates the setting can be applied to the field name. 
  • A RED 'x' (icon-x-red.png) indicates the setting is required and cannot be changed.
  • An ORANGE asterisk (*) next to a field name in BOLD indicates the setting for this field name cannot be customized.

Answer

The table below details the settings that are supported by the configurable fieldsets function in the project's RFIs tool. 

Field Name Required Optional Hidden
Assignees icon-green-checkmark.png icon-x-red.png icon-x-red.png
Cost Code icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Cost Impact icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Distribution icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Drawing Number icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Due Date icon-green-checkmark.png icon-x-red.png icon-x-red.png
Location icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Private icon-green-checkmark.png icon-x-red.png icon-x-red.png
Project Stage icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
RFI # icon-green-checkmark.png icon-x-red.png icon-x-red.png
RFI Manager icon-green-checkmark.png icon-x-red.png icon-x-red.png
Received From icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Reference icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Responsible Contractor icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Schedule Impact icon-green-checkmark.png icon-x-red.png icon-x-red.png
Spec Section icon-green-checkmark.png icon-green-checkmark.png icon-green-checkmark.png
Subject icon-green-checkmark.png icon-x-red.png icon-x-red.png

See Also