Which cost code formats are supported by Procore + Sage Intacct?
Answer
You must use standard Sage Intacct® cost codes in order to sync them with the Procore + Sage Intacct® connector. Procore supports all cost code section rules from Sage Intacct®. For example, if you changed the format of your Sage Intacct® cost codes (e.g. 12-3456-789). However, Procore does not support non-sectioned cost codes (e.g. 1234567) where the first part of the code does not reference a specific division.
Project-specific cost codes can be entered in Sage Intacct® and will appear in Procore during the next data sync. For projects using project specific codes in the Original Estimate, you must first set up the jobs in Sage Intacct® and sync then into Procore. Currently, you cannot create project-specific or special cost codes in Procore and export them to Sage Intacct®. Since cost codes are always being synced from Sage Intacct® to Procore, you can add new cost codes throughout the project, as needed.