How are the date columns in submittal custom reports calculated?

Answer

  • Approver Due Date Variance
    • When a Submittal is Closed, this column is equal to Approver Return Date - Approver Due Date
    • When a Submittal is Open, this column is equal to Current Date - Approver Due Date
  • Approver Returned Date Duration
    • When as Submittal is Closed, this column is equal to Approver Returned Date - Approver Sent Date
    • When a Submittal is Open, this column is equal to Current Date - Approver Sent Date
  • Ball in Court Duration
    • When a Submittal is Open, this column is equal to Current Date - Ball in Court Sent Date