Respond to an RFQ on Behalf of an RFQ Recipient
Back | Current Lesson - 18/29 | Next |
After an RFQ is created, there are two ways that the assigned vendor or subcontractor can submit a response to Procore. You can also enter a response to an RFQ on their behalf, if the recipient has provided you with a quote detailing the schedule and/or cost impact for the change event outside of the Procore web application.
- Navigate to the Change Events tool.
- Locate the desired change event and click the link in the RFQ column.
Notes:- If the recipient has NOT yet responded, the link reads RFQ Sent.
- If the recipient has responded to the RFQ, but its status has not been updated, the link shows the RFQ Amount.
- Click the RFQs tab. To filter the RFQs in the list, choose one these options:
- To view RFQs in the Out for Pricing status, choose Status in the Add Filter drop-down list and then select Out for Pricing. This moves the Ball In Court responsibility to the assignee.
- To view RFQs that are being revised, choose Status in the Add Filter drop-down list and select Revise & Resubmit. This moves the Ball In Court responsibility to the assignee.
- If an RFQ has not yet received a response, a banner appears at the top of the RFQs tab. You can click the appropriate link to respond to that RFQ on behalf of the assigned party.
- Click Post Response.
Notes:- Once the response is posted, the status will automatically update to Under Review.
- The system updates these areas with the posted response: the Response section of the RFQ, the RFQ column in the Change Events log, and the RFQs tab.