Skip to main content
Procore

Edit a Change Event

Back Current Lesson - 13/29 Next

You can edit a change event using the options in the Change Events tool. However, you cannot edit the cost code, cost type, or contract number if it has been linked to a Prime Contract Change Order (PCCO), commitment, Commitment Change Order (CCO), Request for Quote (RFQ), or budget modification. 

  1. Navigate to the project's Change Events tool.
  2. Locate the desired change event and click Edit

    edit-button2.png
     
  3. Modify the desired fields. To learn about each field, see Create a Change Event.
    Note: You will not be able to edit the Cost Code, Cost Type, or Contract # once the line item is linked to a PPCO, CCO, Commitment, RFQ, or budget modification.
  4. Click Update to save your changes.