Add a Related Item to a Change Event
Back | Current Lesson - 12/29 | Next |
Note that if you have created a CE from an RFI or SI, the related item will already be added. This is why it is recommended you always create CEs from their source.
- Navigate to the project's Change Events tool.
- Click Edit next to the change event that you want to add the related item to.
- Click Related Items.
- Click Edit.
- Complete the following fields:
- Type. Select the type of item you would like to relate to the change event. (Note: You can only add items that are already in Procore. You can choose from a long list of items like bids, RFIs, productivity log, prime contract change order, or a task.)
- Description. Once you choose a type, the drop-down menu under 'Description' will populate with the items in your project's Procore account that match the type, or you will see an empty field where you can enter your own description.
- Date. The date will automatically populate with the date that the item was created in Procore.
- Notes. Add any notes related to this item.
- Click Add.
- Click Save.